A factory solar RFQ should make every bidder quote the same site and the same work. Start with the factory's electricity bills, tariff and connection details, roof drawings, electrical single-line diagram, production schedule and the documents you still do not have. Ask each EPC to state its proposed DC kWp and AC kW, tie-in point, meter arrangement, structural and electrical responsibilities, approvals, equipment models, exclusions and price basis. The downloadable RFQ template gives you those fields and a three-bid comparison sheet. It is a buyer's blank procurement aid, not a ready-to-sign technical specification.
Download the factory solar RFQ template: PDF. The document downloads directly from this page without a form. Print it or annotate it in a PDF editor; it has no interactive fields. If you want Heaven Green Energy to prepare a plant-specific proposal, use the separate Get a load-based proposal for my plant form linked to industrial solar.
What this RFQ is for
A request for quotation is most useful when you already know the site well enough to ask comparable questions, but not so well that you have prematurely dictated an unsafe design. It tells bidders what documents they can rely on, what they must verify, what output they must submit and how you will compare the offers. The template begins with the buyer's site information, moves to design basis, connection and approvals, then equipment, commercial schedule and bid evaluation. It leaves bracketed fields blank rather than inventing a fictional plant or assuming every factory has the same roof.
The purpose is to make a price comparison explainable. A quote with a lower total may exclude roof reinforcement, a transformer-side cable run, a revenue-meter change or a shutdown. A quote with a larger proposed array may forecast more exports than the chosen metering route can adjust. A quote with a long warranty headline may not name which company actually stands behind the module, inverter and workmanship obligations. These differences cannot be resolved by dividing each bid by its stated kWp alone.
The RFQ is not an EPC contract. It does not specify legal remedies, liquidated damages, insurance or tax treatment for your company. Those need buyer-side legal, tax and procurement review. It also does not certify the roof or tell the utility which connection to approve. The buyer can use it to collect evidence before a later technical and contractual decision.
Give every bidder the same evidence pack
Attach the same 12 months of electricity bills to all invitees and identify the relevant tariff code, utility, consumer number, supply voltage and contract demand with its unit. A monthly bill gives scale and tariff category; interval data, if available, gives the operating pattern a solar model needs. A factory that runs continuously, a dyeing unit with batch production and a plant with a long weekly shutdown may all have similar monthly kWh but different daylight self-use. Where an interval file is unavailable, state that plainly and require bidders to disclose how they estimated daytime load.
Attach the latest electrical SLD, or say that it is unavailable and must be surveyed. Mark utility meter, CT/PT, transformer, main bus, major boards, diesel generators, APFC or capacitor equipment, and any critical loads that cannot be interrupted. Bidders then have a starting point to discuss where solar might connect. If the SLD is old, identify its revision and known changes; the final design must be reconciled to the actual installation. A point of connection selected from a roof photograph is not an engineering basis.
Supply a roof drawing with dimensions and major exclusions. Mark skylights, vents, AC equipment, fragile or corroded sheets, access routes, parapets and areas controlled by another tenant. If you have no certified structural drawings, say so. The bidder should identify who performs the assessment and what sign-off will be delivered. The RFQ's roof field asks for usable area, not just gross shed area. That distinction prevents a large theoretical kWp number from becoming an unexamined commitment.
Finally, give production constraints. Which shifts run on ordinary weekdays? What happens on Sundays or holidays? Which switchboards can be isolated, and when? Who signs a permit to work? If a tie-in requires a planned shutdown, the scope should name that dependency. The RFQ does not promise that installation can occur with no production interruption; it asks bidders to show the method and likely outage conditions.
| Buyer evidence | Why a bidder needs it | If it is missing |
|---|---|---|
| Twelve monthly bills and tariff code | Establishes billing baseline and correct utility category | Bidder must label energy and tariff assumptions |
| Interval load data | Shows daylight use, low-load periods and possible export | Bidder must state how the load profile was estimated |
| Current SLD | Locates feasible tie-in and protection questions | Survey and drawing update become explicit scope |
| Roof plan and condition | Separates gross and usable area; identifies structure | Structural survey and unknown roof work become dependencies |
| Shutdown and permit rules | Determines connection sequence and production impact | Bidder must qualify programme and tie-in price |
This table is a preparation checklist, not a claim that all buyers already possess those records. A good RFQ exposes missing evidence early, because a later variation can be more expensive and disruptive than a careful survey now.
Ask each EPC to explain its proposed capacity
The template requests DC nameplate capacity in kWp and AC inverter capacity in kW as separate numbers. They are different quantities and should not be swapped in a comparison. The EPC should identify the proposed module and inverter models, module dimensions, DC:AC ratio, string design basis and expected clipping. The roof layout should show the actual module rows and access routes, rather than a rounded kWp based only on area.
The energy estimate should show its inputs and limits. Ask for weather and irradiance source, orientation, shading, module temperature, soiling, electrical losses, inverter availability and degradation assumptions where they affect the offer. NREL PVWatts demonstrates how PV production modelling depends on location, system design and loss inputs; a bidder should state its own chosen method. A single annual kWh number, without hourly or interval matching to the factory's load, is not enough to understand direct self-use and export. That is especially important for an HT plant with production cycles and a potentially material demand component on its bill.
Request at least one normal production day and one low-load day in the model. The purpose is not to make the RFQ longer for its own sake. It reveals whether the proposed size depends on uninterrupted daytime production. If a plant shuts down weekly, a roof-maximising system can export heavily on that day; the applicable settlement rule may treat those exports differently from electricity used directly inside the plant.
For Gujarat projects under GERC Notification 11/2026, bidders must name the proposed metering arrangement and the clause they use for capacity and settlement. For non-residential net metering, the regulation limits export adjustment in a billing period to 30% of energy imported from the grid, with excess beyond the limit lapsed, subject to the regulation's details and applicable banking charges. The rule also contains capacity bands and a battery condition for certain capacity above contract demand. An RFQ issued in 2027 should not cite an old 2016 rooftop rule as though it still governs a newly commissioned installation. The utility and project adviser must confirm the final route. GERC Regulations 4.1, 4.9, 8 and 9.1.5.
Make the point of connection and approvals visible
A rooftop array has to join the plant's electrical system at a point that the design and competent authority accept. The quote must therefore include a marked SLD with the proposed tie-in, revenue and generation meters, CT/PT, transformer, isolation and protection. Ask whether the existing board has the required rating and space, whether a cable route crosses production areas and whether switchgear or transformer modification is included. If a bidder prices an LT bus tie-in and another prices a more complex connection, the scope difference belongs on the comparison sheet.
Metering deserves a separate response. The 2026 GERC regulation describes generation and bidirectional meter readings for net metering, while its model agreement allows additional metering equipment where specified by the licensee and other authorities. The RFQ asks who supplies, tests and documents the actual meter and CT/PT scheme. It should not assert that the existing import meter is already sufficient. GERC Regulations 9.1.3–9.1.4 and model agreement clause 6.
Electrical approval is not the same as energy-settlement approval. The 2026 regulation's activity chart calls for Chief Electrical Inspector installation charging approval whenever applicable, meter/CTPT testing certificates and protection evidence at the relevant stage. A bidder should identify the actual approvals, their owner, the documents it will submit and the point at which the plant may be energised. A generic sentence saying “all approvals included” does not allocate responsibility. The RFQ therefore has a row for DISCOM application, CEI/CEIG review, certificates, meter work and commissioning. GERC 2026 activity chart; CEA distributed-generation connectivity standards.
The distribution licensee may also require network strengthening or charge for it under the 2026 framework. The bidder should separate any estimated utility amount from its EPC price, state whether the estimate has actually been issued and identify who bears a change. That keeps an uncertain external charge out of a falsely fixed total. GERC Regulation 6.4.
Compare equipment and commercial boundaries
The equipment schedule asks for exact models, ratings, quantities and named warranty providers. “Tier-one module” or “premium inverter” is not a substitutable part number. Ask what mounting material is proposed for the actual roof, how penetrations or clamps preserve weatherproofing, and whether cable trays, earthing, surge protection, ACDB/DCDB, monitoring and labels are included. The final engineering team must check model datasheets and compatibility; the RFQ simply forces those choices into the open.
For price, ask every bidder to show an itemised ₹ amount and identify taxes separately. This template deliberately does not contain a generic GST rate or Heaven Green price. The correct tax classification depends on the supplied goods, services and contract, and should be reviewed for the actual transaction. Also ask for utility fees, roof repairs, civil works, shutdown assistance, testing, commissioning and handover as individual included or excluded items. A bidder can then quote a base scope and explicit alternatives rather than burying uncertainty in a footnote.
Programme dates should follow dependencies. A roof survey precedes final mounting design; an electrical review precedes a final tie-in; utility feasibility and approvals precede energisation. Ask for the bidder-controlled activities and identify utility or buyer dependencies separately. Do not compare a promise of “commissioning in 30 days” with another contractor's realistic sequence without reading what each one assumes. The page cannot promise a Heaven Green response or installation timeline without client confirmation.
The bid comparison sheet at the back of the PDF contains three columns. It is intentionally qualitative. A single numerical score would be difficult to defend without buyer-defined weights and verified technical equivalence. Use the sheet to record whether each bidder has priced the same plant, named the same authority route, and taken ownership of the same difficult work. After clarification, the buyer can apply its own commercial and technical evaluation process.
How to use the PDF in a real procurement
First, print the PDF and write in the bracketed fields, or annotate it in a PDF editor; it does not contain interactive form fields. Attach the documents listed in section 1. Replace brackets with facts or the phrase “not available; bidder to verify”. Do not leave a blank that a contractor might treat as permission to assume the most convenient answer. Have the plant electrical and maintenance teams check the SLD revision and the production windows.
Second, send the same PDF and evidence pack to every bidder. Set one clarification deadline and distribute answers to everyone if your procurement rules permit it. When a bidder asks about roof strength, do not answer from memory: give the drawing or flag the structural survey as required. When a bidder asks about export, ask it to identify the current rule and mechanism rather than selecting one on the buyer's behalf without explanation.
Third, review each returned drawing, energy model and price schedule against the comparison sheet. Mark included, excluded, assumed or subject to utility estimate for every material line. Recalculate any kWp and AC kW quoted from the equipment schedule. Confirm whether a forecast uses direct self-consumption, export credit or both. Ask for a revised price only after the bidder has answered technical clarifications, or the new total will still conceal different scopes.
Finally, have your electrical, structural, financial and legal reviewers approve the project-specific specification and contract. This template is a starting structure for that work. It cannot approve a roof, utility connection, equipment choice, tariff treatment, warranty or financial result. An honest RFQ can still save time: it tells every participant exactly what remains to be proved before a factory commits.
Questions about the download
Is the RFQ template a finished solar tender? No. It has fields for the buyer and EPC to fill and questions the site's advisers must resolve. The final tender needs the real drawings, site rules and contractual terms.
Do I need to give contact details to download it? The PDF is available directly from this page. A download-request form may be offered separately for visitors who want help, but the promised file must not be replaced by a lead form or a teaser.
Can I send it to multiple EPCs? Yes, as a blank buyer aid. Send the same evidence pack and clarify the same questions for each. Its value comes from comparable responses, not from the Heaven Green name on the file.
Does it include a price schedule? It includes the categories and exclusions each bidder should price. It has no generic project price or payback period because those depend on surveyed site conditions, models, metering and contract scope.
Does it decide whether my plant needs CEI approval? No. It tells the bidder to identify the competent authority and provide the required evidence. The 2026 regulation uses “whenever applicable” for charging approval in its activity chart, so the answer must be checked for the actual project.
What should I do if bids are far apart? Compare DC and AC capacity, usable roof area, connection point, utility/inspection scope, equipment models, tax treatment, exclusions and production-shutdown assumptions before treating the difference as a discount. The comparison sheet was designed to reveal those differences.
Get a plant-specific proposal
Download the factory rooftop solar RFQ PDF, print or annotate what you know and mark the rest for review. If you want Heaven Green Energy to discuss a bid based on your actual bills, roof and SLD, use the separate industrial solar enquiry with the label Get a load-based proposal for my plant. The enquiry form below is separate from the direct PDF download. You can also call +91 63904 05060 to discuss the documents needed for a proposal.