Interactive factory solar guide

Compare factory solar quotes side by side

Normalise two pre-tax EPC quotes on one declared scope. Unpriced omissions keep the comparison incomplete.

Rule or method checked 23 November 2026. US DOE provider-selection guide (procurement method only)

Bid 1
Bid 2

Calculation runs in this browser. The figures you enter are not sent with this form.

Two factory solar quotes with the same headline capacity can buy different systems. Enter each bid's DC capacity, pre-tax EPC price and documented prices for missing scope. The comparison tool then shows a scope-adjusted total and price per DC watt. It does not choose an EPC for you: a bid with unpriced roof, grid or maintenance work remains incomplete until the bidder or a qualified third party prices it.

Tool inputs: common site/scope reference, bidder name, proposed DC kWp, quoted price excluding tax, priced omissions and unpriced omissions. Output: scope-adjusted pre-tax total, pre-tax price per DC Wp, and a warning if the bids cannot yet be compared. The comparison runs in the browser, and the result is shown before any enquiry form.

First decide what the two bids are meant to cover

“Compare solar quotations” sounds like an arithmetic task, but arithmetic comes after scope. One bidder may include roof strengthening, a metering panel, structural calculations, monitoring and annual maintenance. Another may exclude all five while advertising a lower price per watt. The buyer needs a common project definition before comparing totals. A quote based on a satellite image is also at a different design stage from one based on a measured roof survey.

Create a one-page reference scope for the site. Name the factory address and electricity connection, roof bays, usable area, known repairs, plant operating hours, electrical point of connection and expected work boundary. Decide whether the project price should include approvals, meters, switchgear work, roof repair, civil works, testing, commissioning, training and handover. If some items are deliberately owner-supplied, list them in every bidder's request. This step makes omissions visible rather than treating them as savings.

The US Department of Energy's provider-selection guide recommends defining evaluation criteria before soliciting proposals. Its US legal and tax context does not apply to a Gujarat factory, but the procurement sequence does: describe the same task to each bidder, then evaluate the responses against it. SECI's rooftop solar tender material similarly makes equipment, drawings, expected output and grid connection explicit fields. A private factory need not copy a government tender, but can learn from the clarity of its schedules.

What the calculator can and cannot compare

The initial calculator normalises documented cost scope. It accepts two prices on the same tax basis and adds any priced work the buyer must procure to make a bid meet the reference scope. It divides the resulting amount by each bid's stated DC module capacity in watts. That is useful for spotting when a lower advertised price becomes a higher complete-scope price. It is not a lifecycle cost model, a generation model, or a verdict on engineering quality.

For example, the tool should not assign a zero cost to an omitted transformer upgrade because neither bidder priced it. Nor should it insert a market-average roof repair price: the roof may need no work or a major redesign. If a mandatory line has no credible price, show incomplete comparison and list the question. The same applies when one bidder quotes a different roof or a different site. A numeric “winner” would be misleading until those differences are resolved.

Tool field Unit or format Why it matters
Common scope reference Text, same for both bids Prevents comparison of different roofs or electrical boundaries
Proposed DC capacity kWp Denominator for price per DC Wp; not inverter AC kW or kVA
Quoted EPC amount ₹ excluding tax Shared price basis; tax treatment is a separate check
Priced omissions ₹ excluding tax, each with a label and source Adds mandatory work excluded from the quote
Unpriced omissions Named list Keeps the result incomplete rather than pretending zero cost
Quote date and revision Date / document ID Shows whether the prices and specifications refer to the same bid version

The page should show units beside every input and tell users that the cost correction is only as reliable as the priced omission they enter. The tool should never store an uploaded bid or commercial amount without a clear privacy and retention decision. A local-only first version can avoid that complexity, but its browser behaviour must be tested.

A worked comparison with illustrative numbers

Suppose both bids cover the same factory roof and each offers 100 kWp DC. Bid A quotes ₹40,00,000 before tax, but excludes a roof-strengthening scope priced independently at ₹5,00,000 before tax. Bid B quotes ₹43,00,000 before tax and includes that same work. The scope-adjusted total is ₹45,00,000 for A and ₹43,00,000 for B. The corresponding values are ₹45 and ₹43 per DC watt. Under this narrow cost comparison, B has the lower complete-scope amount even though A's advertised EPC price was lower.

Illustrative bid Quoted pre-tax amount Documented mandatory add-on Adjusted pre-tax amount DC size Adjusted ₹/DC Wp
A ₹40,00,000 ₹5,00,000 roof work ₹45,00,000 100 kWp ₹45
B ₹43,00,000 Included ₹43,00,000 100 kWp ₹43

These are invented teaching inputs, not a Heaven Green price, an observed market rate, a project result or a recommendation. The arithmetic is adjusted price = quoted price + documented mandatory add-ons; adjusted ₹/DC Wp = adjusted price ÷ (DC kWp × 1,000). The tool's tested reference function implements this limited calculation. It would refuse to rank A and B if the roof work were only described as “by owner” with no price. A lower adjusted total also does not settle the decision if the equipment, yield model or contract risks differ.

This example explains why the calculator asks for a pre-tax base. A bidder's GST statement can be correct for its scope and still use a different valuation treatment from another bidder's proposal. Ask each for the same tax breakdown and have the finance team check it. Do not make the tool guess tax from a single percentage. The calculator compares a declared cost basis and flags the rest for human review.

Compare DC size, AC size and expected generation separately

One quote may say “100 kW plant” and mean 100 kWp of modules; another may mean 100 kW of inverter AC capacity. These are not identical. Record the module make and model, module count and individual Wp rating, then multiply to obtain DC kWp. Record the inverter model, count, AC rating and any proposed export limitation separately. The DC-to-AC ratio, clipping assumption and operating conditions can change expected production. A denominator error makes every price-per-watt comparison wrong.

For expected generation, ask for monthly—not only annual—figures and the model inputs: location, orientation, tilt, shading, temperature, soiling, downtime and degradation assumptions. The NREL PVWatts documentation shows why a production estimate depends on input choices. Do not treat one bidder's higher projected kWh as better until both use comparable weather and loss assumptions. A factory's working shifts also affect how much generation is used directly and what is exported under its approved arrangement.

If a bid states a performance ratio or generation guarantee, read the measurement procedure. What irradiance instrument is used? What period counts? What exclusions apply to grid outages, curtailment or roof access? Who maintains the meter and resolves a disputed reading? SECI's rooftop RfS example includes a PR measurement format; it illustrates that a number needs a defined method. It is not a default performance promise for a private industrial project.

The roof and structure column cannot be a checkbox

For a factory shed, the roof is often the largest hidden scope difference. Ask which bays each bidder includes, whether a structural engineer has reviewed the roof, what drawings or measurements informed the design, and what happens if strengthening is needed. The mounting schedule should name the actual sheet profile, fixings, purlin spacing and wind assumptions. “Structure included” does not tell you whether the price includes strengthening the existing shed, only rails above it, or neither.

Compare access and waterproofing too. One bidder may leave gutters, vents and skylights reachable; another may fill the available roof footprint. A low initial price can become expensive if every cleaning or repair needs module removal. A proposal should identify existing leaks before work and show who owns new penetrations. Any roof work below the panels needs the plant owner's safety and operations review as well as the structural decision.

The calculator treats unpriced roof work as an unknown, not zero. A bid can have an attractive ₹/Wp result while still being unready for award. An exception note should say exactly which drawing, site visit or engineered opinion is needed to price the scope. That is more useful than a coloured score that makes a guess look objective.

Electrical boundary and current Gujarat rules

Each bid should state the electrical point of connection, existing switchgear assumptions, meter/protection arrangement and work needed before synchronisation. An LT bus, transformer secondary or dedicated panel may lead to different cable routes, shutdowns and protection work. A bid that excludes the plant's switchgear change is not comparable with one that includes it until the change is priced. The same is true for a DISCOM-driven network-strengthening estimate.

For a Gujarat project planned after October 2026, identify the applicable GERC Grid Interactive Distributed Renewable Energy Sources Regulations, 2026 and the distribution licensee's current procedure. The regulation repeals the older 2016 rooftop rules. It does not turn every proposed plant into an automatically approved connection. A bid should name its metering choice, export assumption, technical-feasibility dependency and responsibility for application fees, drawings, meters and inspections. The contract should say who pays if required network work changes the scope.

Do not borrow a connection charge, export credit or process timeline from another factory's quote. Tariff and approval conditions depend on consumer category, licensee, capacity, connection and commissioning date. For an HT factory, bill and protection consequences are especially important. Our industrial solar service is the matching buyer route. Use the enquiry form for a site-specific proposal, separate from this cost comparison.

Equipment tables need exact models

A quote saying “Tier 1 panel” or “three-phase inverter” is not a complete specification. Record the exact module and inverter model identifiers, quantity, rated capacity and dated datasheet version. Ask about the minimum technical parameters that matter for the design: module dimensions, electrical limits, fire and structural fit, inverter MPPT/current/voltage range, grid protection and environmental rating. A different module footprint can change the number of panels that physically fit around skylights and walkways.

Also identify alternatives and substitutions. Can the EPC change a module after purchase order? If so, what minimum equivalence and owner approval apply? A lower quote may assume an available model while a higher one names a model already reserved. Do not present an unverified stock or warranty claim as a fact. Ask for a written equipment schedule and the actual manufacturer's warranty documents for the proposed models, including who handles labour and freight during a claim.

Equipment question Bid A answer Bid B answer Where to verify
Module model, count and Wp Fill from bid Fill from bid Dated manufacturer datasheet and BOQ
Inverter model, count and AC rating Fill from bid Fill from bid Dated manufacturer datasheet and SLD
Mounting material and fixing type Fill from bid Fill from bid Structural drawing and material schedule
Protection and metering components Fill from bid Fill from bid SLD, utility approval and BOQ
Substitution rights Fill from contract Fill from contract Purchase order and technical annexure

This table is intentionally blank. It is a buyer's comparison structure, not a claim about any named EPC or product. The final tool may offer these fields as a non-scored checklist beside the price calculation. A single automatic grade would hide the difference between missing evidence and a genuinely poor design.

Installation schedule and factory disruption

Ask both bidders for a sequence that separates roof preparation, mounting, DC work, inverter and AC work, testing, authority approval and energisation. Which tasks occur over operating production lines? Which require a shutdown? Who arranges lifting equipment, isolation permits and EHS access? A statement that installation will not affect production needs a site-specific method and an agreed electrical tie-in plan.

Compare dates as dependencies, not promises. A bidder may assume a quick utility approval or immediate transformer availability; another may include those risks in a longer programme. Note which approvals are buyer-supplied, which are EPC-supplied and which depend on the authority. If the proposal is contingent on a roof engineer's report, show the decision date and the price effect of a failed report. The procurement team can then identify a real schedule advantage instead of comparing two unqualified completion dates.

The same distinction applies to payment milestones. A quote with a lower total but most payment due before equipment delivery is a different commercial risk from one that ties payment to inspected milestones. Ask the finance and legal teams to compare security, retention, delay terms, change control, acceptance tests and dispute process. This page does not recommend a fixed contractual term; the relevant terms depend on the project and signed documents.

Operation, monitoring and handover

A factory will live with the system after the installation team leaves. Compare monitoring scope: is it inverter generation only, or does the proposal include revenue-grade meter data, irradiance and alarms? Who gets dashboard access, who owns data and how long is it retained? Ask for a maintenance schedule that covers cleaning, electrical inspections, roof fixings, corrosion and safe access. A “five-year O&M” line is incomplete without tasks, frequencies, exclusions and responsibility for consumables and replacement labour.

Handover documents should include as-built layout, SLD, equipment model and serial list, protection settings, test reports, authority approvals, meter documents and operating instructions. US DOE procurement guidance treats technical specifications as something that follows the system from solicitation through commissioning. The same discipline is useful here, while Indian standards and the actual DISCOM govern the technical content.

If one quote includes detailed handover and another merely says “commissioning complete,” request a revision. These outputs are not decorative paperwork: they are what a maintenance team needs to isolate a fault, check a warranty claim and explain the plant to a future electrical contractor. An EPC quote comparison should price the plant that can be operated, not only the plant that can be installed.

What to do with an incomplete or cheaper bid

The tool should return one of two clear states. Comparable on declared cost scope: both bids share a scope key and no mandatory omission is unpriced. It may show the lower scope-adjusted pre-tax amount without calling that bidder the best EPC. Incomplete: at least one required scope item is unpriced or the site/scope differs. It should list the exact gap and ask for a revised bid or an independent price. There is no hidden score or invented quality weighting.

When the cheaper adjusted quote still has a weaker design, list the design issue separately. For example, a module model may be unsupported for the roof layout, or an export assumption may not match the factory's actual load. A buyer can ask for a correction or reject the bid on technical grounds. Do not add a made-up rupee penalty to the calculator merely to force the result you prefer. A qualitative issue should stay visible as a qualitative decision until it becomes a documented scope and price item.

If the bids have different DC capacities, the per-Wp display helps orient the reader but does not by itself normalise output or economics. The larger system may export more, encounter a roof constraint or need a different inverter configuration. Request both bidders to quote the same target design or compare each as a separate investment case with its own generation and bill model. A larger denominator can make ₹/Wp look better even when the plant is a worse fit for the factory.

The decision to make before asking for another proposal

Use the comparison to produce a short clarification list: missing roof sign-off, connection assumption, exact module model, meter scope, maintenance term, performance method or price basis. Send the same questions to both bidders and preserve their written answers as contract annexures. Then update the tool with only the documented amounts. This turns a price comparison into a procurement record that another person can review later.

Heaven Green Energy can respond to the same reference scope. Get a load-based proposal for my plant through the planned industrial form, or call +91 63904 05060. Share your bills, roof information and the bid questions you want answered. The form and page-specific WhatsApp route require live testing before this page can publish. A quote comparison can expose the important differences; it cannot replace structural, electrical, financial or legal review of the final contract.

Discuss your plant with an engineer

Share the site, bill or quote behind your calculation so the proposal uses real inputs.

Call WhatsApp