Use this calculator to estimate the demand-charge portion of one DGVCL HTP-I factory bill under the FY 2026–27 tariff. Enter the contract demand and the month's actual maximum demand in kVA. The calculation applies the tariff's billing-demand floor, tiered charge within contract demand, and the charge for demand above contract demand. It does not calculate your whole electricity bill or prove what solar will save.
Tariff checked: GERC's DGVCL tariff order for FY 2026–27, clauses 11.1 and 11.4, issued 25 March 2026; checked 23 November 2026. Choose this tool only if your bill says DGVCL HTP-I. A Torrent Power, LTMD, seasonal HTP or other category bill needs its own calculation.
Enter the two numbers from your bill
The input labelled contract demand is the demand agreed for the electricity connection. The input labelled actual maximum demand is the maximum demand recorded by the meter for that billing month. For the DGVCL HTP-I tariff, both should be in kVA. Do not enter your total monthly energy consumption in kWh, a solar plant's kW rating, or the maximum demand from a different month. The bill commonly shows these values in separate demand and billing-detail areas; use the units printed beside them.
The tool's interface should state its exact scope beside the inputs: DGVCL, HTP-I, FY 2026–27. It should default to blank fields, accept finite non-negative actual demand and a contract demand of at least 100 kVA, and reject a comma or unit string if the browser cannot parse it safely. A value of zero actual maximum demand can be used to understand the billing floor, but it does not imply that a real connected factory can receive a zero-demand bill. A zero contract demand is invalid for this tariff category.
The output should show the billing demand chosen by the tariff, the amount within contract demand, the kVA above contract demand, the within-contract charge, the excess-demand charge, and their sum. All output rupee values should be rounded to two decimals for presentation only; the core calculation should use unrounded numbers. A copyable breakdown is more useful than a single large “penalty” number because it lets the buyer compare each line with the actual bill.
The exact DGVCL HTP-I formula
For FY 2026–27, DGVCL HTP-I billing demand is the highest of three values: actual maximum demand established during the month, 85% of contract demand, and 100 kVA. This is clause 11.4 of the official tariff order. The tariff applies to regular HT consumers contracted for 100 kVA or above whose purpose is not covered by another HT category. The maximum demand definition concerns an averaging interval measured by the meter, not a millisecond spike seen on a machine display.
Once billing demand is known, split it at contract demand. The portion up to contract demand uses three monthly rates: ₹150 per kVA for the first 500 kVA, ₹260 per kVA for the next 500 kVA, and ₹475 per kVA above 1,000 kVA. The portion of billing demand above contract demand is charged at ₹555 per kVA per month. The excess charge is the line many people call an “MD penalty”; the order calls it a demand charge for billing demand in excess of contract demand.
| DGVCL HTP-I FY 2026–27 component | Rate | Applied to |
|---|---|---|
| First 500 kVA within contract demand | ₹150/kVA/month | The first tier of min(billing demand, contract demand) |
| Next 500 kVA within contract demand | ₹260/kVA/month | The portion above 500 and up to 1,000 kVA |
| Above 1,000 kVA within contract demand | ₹475/kVA/month | The portion above 1,000 kVA, still within contract |
| Billing demand above contract demand | ₹555/kVA/month | max(0, billing demand − contract demand) |
The rates in the table are from GERC's March 2026 order, tariff clauses 11.1.1 and 11.1.2. They are not a tariff for every Gujarat factory. The formula also does not include energy charges, time-of-use charges, power-factor adjustment, electricity duty, taxes, rebates, arrears or other bill items.
Work through a 500 kVA example
Suppose a DGVCL HTP-I factory has a 500 kVA contract demand and records 600 kVA actual maximum demand in one month. These are illustrative inputs, not a Heaven Green project or customer bill. The billing-demand candidates are 600 kVA actual, 425 kVA as 85% of contract, and 100 kVA as the minimum. The highest is 600 kVA, so the calculator uses 600 kVA.
The first 500 kVA are within contract demand and fall entirely in the first rate tier: 500 × ₹150 = ₹75,000. The remaining 100 kVA are above the 500 kVA contract: 100 × ₹555 = ₹55,500. The estimated total demand charge is ₹75,000 + ₹55,500 = ₹1,30,500. The excess-demand component is ₹55,500. It would be inaccurate to call the total ₹1,30,500 an “excess penalty”; ₹75,000 is the ordinary within-contract demand charge.
Now keep the same 500 kVA contract but enter only 100 kVA actual maximum demand. The bill does not use 100 kVA as billing demand under this tariff because 85% of contract demand is 425 kVA. The selected billing demand is 425 kVA, and the demand charge is 425 × ₹150 = ₹63,750. There is no above-contract component. This example explains why a low-production month can still show a substantial demand charge and why one should not estimate demand charges from actual demand alone.
The tool shows the demand breakdown beneath the inputs and cites the tariff period. Its calculation core has test cases for both scenarios and the 100 kVA boundary.
Where the 500 and 1,000 kVA tiers matter
A common spreadsheet error is to charge every kVA at the rate of the highest tier. The tariff's wording separates the first 500, the next 500 and the portion above 1,000, so the within-contract part is progressive. Consider an illustrative 1,200 kVA contract with a 1,300 kVA actual maximum demand. Billing demand is 1,300 kVA because it is greater than 85% of contract (1,020 kVA) and the 100 kVA floor.
Within contract demand, the first 500 kVA cost 500 × ₹150 = ₹75,000. The next 500 cost 500 × ₹260 = ₹1,30,000. The final 200 within contract cost 200 × ₹475 = ₹95,000. Those portions total ₹3,00,000. The 100 kVA above the 1,200 kVA contract cost 100 × ₹555 = ₹55,500. The estimated demand-charge total is ₹3,55,500. Applying ₹475 to all 1,200 kVA would overstate the within-contract component; applying ₹555 to all 1,300 kVA would be even further from the tariff structure.
| Illustrative input set | Billing demand | Within-contract charge | Excess-demand charge | Total demand charge |
|---|---|---|---|---|
| Contract 500 kVA; actual 600 kVA | 600 kVA | ₹75,000 | ₹55,500 | ₹1,30,500 |
| Contract 500 kVA; actual 100 kVA | 425 kVA | ₹63,750 | ₹0 | ₹63,750 |
| Contract 1,200 kVA; actual 1,300 kVA | 1,300 kVA | ₹3,00,000 | ₹55,500 | ₹3,55,500 |
Every row in this table is a hypothetical test case using the cited FY 2026–27 DGVCL HTP-I tariff. They are not typical bills, company performance results, or an estimate for your connection. The tool should keep the inputs visible next to the outputs to prevent an example from being mistaken for a quotation.
Maximum demand is a measured interval, not monthly units
Electricity bills mix different quantities: kW or kVA of demand, kWh or kVAh of energy, and rupees charged under several headings. Maximum demand is the highest average demand over the meter's specified measurement period during the billing month. The DGVCL HTP-I tariff clause 11.7 describes consecutive 30- or 15-minute periods, and a possible three-minute period for certain grid-parallel consumers who have opted for it and have the required meter. Read your sanctioned arrangement and meter record; do not assume every factory uses the same interval.
A short machine start may appear as a sharp instantaneous current spike without setting the month's billed maximum demand. A sustained simultaneous load can set a new interval average and affect the demand-charge line. That distinction matters when deciding whether to stagger motor starts, alter a process schedule or investigate a real power-factor issue. The tool cannot tell why the maximum occurred; it only reproduces the tariff arithmetic from two bill inputs.
An operations team trying to manage demand should look at interval data and timestamps, not just a final monthly maximum. If the maximum happened after sunset or during a cloudy shift, ordinary rooftop solar may not have reduced it. If it happened during strong generation but the factory's electrical system or inverter configuration limited self-consumption, an engineer may find a different explanation. Do not infer from one bill that a solar plant will erase the above-contract charge.
What solar can and cannot change on this bill line
On-site solar can reduce grid import while it generates. Whether it reduces recorded maximum demand depends on the time of the highest demand interval, the solar output during that interval, the metering arrangement and the site's electrical topology. If a factory's maximum is driven by a night shift, a midday PV array will not address that interval directly. If maximum demand occurs on a sunny weekday, solar may reduce grid draw, but clouds, maintenance, inverter limits or a later evening peak can still determine the monthly maximum.
The 85% billing-demand floor is another limit. Even if actual measured maximum demand falls well below contract demand, the tariff may bill 85% of contract. A proposal that multiplies solar generation in kWh by the excess-demand rate in ₹/kVA mixes energy and power and is not a valid saving calculation. The demand component needs an interval comparison and an assessment of what the maximum would have been without and with solar. That requires data and an explicit method, not an annual generation chart alone.
There may be a separate case for reviewing contract demand, but reducing it without examining process peaks and future expansion can expose the factory to excess-demand charges in another month. The decision should compare a representative set of bills, interval peaks, production plans, permitted contract changes and the current tariff. The industrial solar page provides the broader project route.
When this calculator is the wrong tool
Do not use the DGVCL HTP-I formula for a Torrent Power bill. The GERC tariff schedule register lists separate 2026 schedules by licensee. Torrent's HTMD tariff uses kW and different rates; copying DGVCL's kVA tiers would produce a confident but wrong result. A DGVCL LTMD consumer also has a separate rate structure and kW units. A seasonal HT consumer has special provisions that can change minimum billing. The tariff category printed on your actual bill is the decisive starting point.
The calculator also does not reproduce a complete bill. It excludes energy charges, time-of-use additions or discounts, power-factor adjustment, demand-related minimum bills beyond the modelled ordinary HTP-I rules, taxes and duties, other levies, meter charges, arrears and credits. The output should be labelled estimated demand charge under the selected tariff, not “your bill” or “your solar saving.” If it differs from the bill's demand-charge line, first verify that the category, contract demand, maximum demand, billing month and meter units match. Then check for a tariff revision or special condition before assuming the bill is wrong.
An invoice challenge is a different task from a calculator comparison. Keep the bill, sanctioned contract, meter reading and any utility correspondence. Ask the distribution licensee for the calculation basis if an item remains unexplained. This page is designed to make the charge legible, not to offer a legal verdict on a disputed bill.
Checks before this tool goes live
The production calculator should present a visible tariff date and a link to the exact GERC order. It should expose the formula in text, not only in JavaScript. It should reject negative, missing, infinite and non-numeric inputs, and show an explanatory validation message rather than silently treating them as zero. It should use inputmode="decimal" for mobile entry, associated labels, a live result region announced to assistive technology, and a responsive breakdown table. If it plots a chart, each bar must match the numeric result and have a text equivalent; a graph is optional because two clear rupee lines already answer the buyer's question.
The calculation core tests a normal excess case, a low-actual-demand floor case, a tier crossing above 1,000 kVA, the 100 kVA category boundary and invalid inputs. These checks verify arithmetic against the cited FY 2026–27 clauses; they cannot validate an individual factory bill or a future tariff change.
Get a load-based proposal for my plant. If you want to understand whether solar could change demand as well as imported energy, share a run of bills and, if available, interval demand data. A site-specific analysis can locate the peak intervals, model solar against them, and state which bill components the system is expected to affect. Do not treat this calculator's demand-charge output as a guaranteed solar saving.