Roughly 80% of rooftop solar installation delays we track at Heaven Green Energy trace back to one root cause — a roof that was not prepared before the installer arrived on site. Hairline cracks that started weeping in the last monsoon, a rusted GI (galvanised iron) sheet that the homeowner planned to replace “next year”, an AC (air-conditioner) outdoor unit blocking the south face, a water tank casting a shadow nobody measured. Each one of these turns a clean two-day install into a two-week back-and-forth, and almost every one is solvable in the four weeks before the technician arrives.
This guide is the field checklist we hand to homeowners during pre-installation calls. It covers what to inspect, what to fix, when to fix it, and what each repair typically costs across RCC (reinforced cement concrete), metal sheet, and Mangalore tile roofs in India.
Direct answer. Preparing your roof for solar installation cuts on-site delays by 80% and protects the 25-year structural warranty. The 8-point checklist covers structural strength, leaks and seepage, waterproofing, surface obstructions, drainage paths, electrical readiness, scaffolding access, and neighbour clearance. Typical pre-prep cost is ₹3,000–₹15,000 and the work needs 2–4 weeks before the installer arrives. Heaven Green Energy’s pre-installation survey catches ~92% of roof issues before they become onsite delays.
Most homeowners think of roof prep as a one-day broom sweep before the panels arrive. It is closer to four weeks of small, sequential tasks — and the cost of getting it wrong is panel removal, slab drilling repair, or worse, a void in the structural warranty.
Why Roof Preparation Drives Installation Success
A residential rooftop solar system in India adds 15–20 kg per square metre (sq m) of dead load on an RCC slab, and 25–30 kg per sq m once you include the mounting structure, cabling, and combiner boxes. That load sits on the roof for 25 years through the worst monsoons, the hottest summers, and the wind events that BIS (Bureau of Indian Standards) IS 875 Part 3 wind load code designs for at around 3 kPa (kilopascals) in most residential zones.
If the underlying surface is already compromised — a slab with carbonation, a metal sheet with rust under the lap joint, a tile course with two broken tiles — installing solar on top accelerates the failure. The mounting feet concentrate point loads. The thermal cycling between hot panel back and cool slab opens cracks. The slow drip becomes an active leak.
A properly prepared roof, by contrast, costs the homeowner ₹3,000–₹15,000 to bring up to standard, takes 2–4 weeks of staged work, and removes almost every category of avoidable post-install problem. The work is mostly civil — waterproofing, minor crack injection, drainage clearance, surface cleaning — and it sits firmly inside what a local mason can do without specialised solar knowledge. The harder part is the sequencing, which is what this guide gives you.
A pre-prepared roof also shortens the actual installation window. For a typical 3 kW residential job in India, a clean roof installs in 2 working days; a roof that needs onsite repair stretches to 5–7 working days, with the installer’s team waiting, the scaffolding renting, and the PM Suryaghar subsidy timeline drifting because commissioning gets postponed.
The 8-Point Pre-Installation Roof Checklist
This is the named framework we use across every residential survey — The 8-Point Pre-Installation Roof Checklist. Eight points, each tied to a measurable pass/fail on the roof, and each with a typical 2–4 week lead time to fix. Run through the list in order. The first three are mandatory; the remaining five are conditional on roof type and site layout.
| # | Checkpoint | What to verify | Typical action |
|---|---|---|---|
| 1 | Structural strength | Slab thickness, age, visible cracks | Civil engineer load opinion |
| 2 | Leaks and seepage | Damp patches on ceiling below | Crack injection, grout |
| 3 | Waterproofing | Membrane condition, age, joins | APP or brush coat top-up |
| 4 | Surface obstructions | Loose items, debris, sand | Clear and sweep |
| 5 | Drainage paths | Khurras, slope, choking | De-choke and slope check |
| 6 | Electrical readiness | DB space, earthing, conduit route | Electrician pre-visit |
| 7 | Scaffolding access | Stair, ladder, hoist route | Plan, clear corridor |
| 8 | Neighbour clearance | Adjacent walls, shading objects | Notify, written NOC |
Point 1 — Structural Strength
The IS 456 standard for RCC design governs RCC slab design in India. Any slab less than 15 years old, constructed to current code with M20 (mix of 20 megapascal compressive strength) concrete or higher, and at least 110–125 millimetres thick, will safely carry 25 kg per sq m of solar load. Older slabs — pre-2005, with hand-mixed concrete or visible rebar staining — need a written opinion from a structural engineer. The opinion costs ₹2,000–₹4,000 and protects both you and the installer.
Look for three warning signs. First, surface spalling — small chips of concrete falling away, exposing rusted reinforcement. Second, ceiling stains below the slab — long brown streaks usually indicate carbonation and rebar corrosion. Third, visible deflection — a slab that visibly sags between supports under furniture or a water tank is not a candidate for additional solar load until reinforced.
Point 2 — Leaks and Seepage
The single most expensive post-install repair is a roof leak underneath an already-installed panel array. Removing 12 panels to access a leak point costs ₹15,000–₹25,000 in labour alone, before any civil repair. Two weeks before installation, do a deliberate water test — flood-test a 2-metre square of the roof for 6 hours and check the ceiling below.
Mark every damp patch with chalk. Inject the visible cracks with low-viscosity epoxy or polyurethane grout — a local civil contractor charges ₹400–₹800 per running metre of crack. Wait one full monsoon-style rain before installation, even if it means delaying by a fortnight. A roof that survives 48 hours of continuous water has earned the right to host a 25-year solar array.
Point 3 — Waterproofing
Most Indian RCC roofs have either an APP (atactic polypropylene) membrane, a brush-applied acrylic coat, or a brick-bat coba layer with a top finish. Membrane life is 7–10 years, acrylic coat 3–5 years, and coba 15+ years if undisturbed. If your waterproofing is at or past its design life, top it up before solar installation — adding panels makes future re-waterproofing harder, because you have to work around the mounting feet.
A top-coat refresh on a 1,000 sq ft (square feet) roof costs ₹8,000–₹14,000 in 2026 prices and adds five years of effective life. Schedule this 3–4 weeks before installation so the new coat has time to fully cure.
Point 4 — Surface Obstructions
Walk the roof and note every loose item — old bricks, plant pots, a broken inverter cabinet from a previous installation, leftover construction sand. The installer’s team needs a clear surface for marking, drilling, and structure assembly. Anything left on the roof gets in the way of measuring tape, levelling, and panel laydown. Clear it the week before; a single afternoon’s effort.
Pay attention to fixed obstructions you might have stopped noticing — old TV antennas, defunct dish receivers, a temporary tarp shed put up during a previous repair. These need to come down. Anything that throws a shadow onto the planned array footprint between 9 a.m. and 4 p.m. directly cuts your annual generation by 5–15%, depending on size and position. The solar panel direction guide explains shading impact in detail.
Point 5 — Drainage Paths
Every Indian RCC roof has at least two khurras (drain outlets) and a slope of 1 in 100 to 1 in 80 leading to them. Solar mounting structures must not block drainage or create dams. Walk the roof during or just after rain — water should reach the khurras within minutes, not pool. Choked khurras get cleared by a plumber in 30 minutes for ₹300–₹500.
If your roof has standing water hours after rain, you have either a slope problem or a choke. Solve it before mounting feet are drilled, because once feet are in, any drainage rework involves removing and re-fixing those feet. For metal roofs, the same logic applies — check that valley gutters at the eave are not silted, and that downspouts flow freely.
Point 6 — Electrical Readiness
Solar adds a new circuit — DC (direct current) cable from the array to the inverter, AC output from the inverter to the meter, and an earth conductor sized per the IS 3043 earthing code. Three things must be in place before the installer arrives. First, the distribution board (DB) needs spare two-pole space for the solar AC isolator. Second, the earth pit per IS 3043 must be either present or marked for new installation — most homes need either a fresh earth pit or a verified continuity check on the existing one. Third, there should be a clear conduit path from the proposed inverter location to the roof, ideally avoiding water tanks or kitchen wet zones.
An electrician’s two-hour pre-visit ₹500–₹1,500 confirms readiness and lists any small interventions — a knock-out for a fresh conduit, a deeper earth pit, an extra MCB (miniature circuit breaker) slot in the DB. This is far cheaper than discovering on install day that the DB is full.
Point 7 — Scaffolding Access
Panels arrive in cartons of two, each carton roughly 2.2 metres long and weighing 25–30 kg. Mounting structure pieces are 2–4 metre lengths of MS (mild steel) or aluminium section. All of this has to reach the roof. Identify the route — the main staircase, a fire escape, a rope hoist from the rear courtyard — and clear it. If the only access is through your living room, plan for floor protection. If the building has a service lift, confirm size and weight limits.
For independent houses, a rope hoist with a pulley at the parapet usually works. For G+3 (ground plus three) and taller flats, the installer brings a small jib hoist. Either way, ensure 3 metres of clear vertical airspace near the hoist point — overhead cables, neighbour’s awning, tree branches all need pre-clearance.
Point 8 — Neighbour Clearance
Solar installations in dense Indian neighbourhoods often touch the boundary of what neighbours can object to — early-morning drilling noise, dust drifting across to their roof, the scaffolding swing leaning over their parapet. A short written NOC (no-objection certificate) from the immediate neighbours on shared walls, signed and dated, is worth the half-hour of polite knocking. It prevents a stop-work order from a peeved neighbour after Day 1.
Some municipal bodies — Mumbai’s BMC (Brihanmumbai Municipal Corporation) is the strict example — also require setback compliance from the building edge for solar arrays on certain building heights. Check local rules; for most independent residential homes, no permit is needed beyond the PM Suryaghar feasibility approval.
Tip
Take dated mobile photos of the roof at every stage of prep — before clearance, after clearance, after waterproofing, after drainage check. These photos go into the installer's site file and form part of the structural warranty record. If a roof issue surfaces in year 8 or year 12, your photos prove the condition at handover.
Roof Type Differences — RCC vs Metal vs Tile
The eight-point checklist applies to every roof, but the specific work — and the cost — varies by roof type. The three common residential surfaces in India are RCC slab (most homes), metal sheet (industrial sheds, modern villas), and Mangalore tile (older houses in the Konkan, Karnataka, and Tamil Nadu belts).
| Roof type | Key prep focus | Typical issues | Pre-prep cost | Suitability for direct mount |
|---|---|---|---|---|
| RCC slab | Waterproofing, drainage, slab opinion | Crack-water seepage, choked khurras | ₹5,000–₹15,000 | Excellent — most installations |
| Metal sheet (GI / colour-coated) | Rust check, fastener integrity, sheet condition | Rusted laps, loose self-drilling screws | ₹3,000–₹10,000 | Good — needs L-foot or clamp |
| Mangalore tile | Structural batten condition, tile fragility | Brittle tiles, soft battens | ₹8,000–₹20,000 | Limited — usually needs ballast or alternate mount |
For an RCC slab, the prep is mostly about waterproofing renewal and structural opinion. Most slabs older than 15 years benefit from a fresh APP or brush-coat layer before solar mounting. Mounting is via cast-in lugs or chemical anchors drilled through the membrane and re-sealed with a butyl tape collar.
For a metal sheet roof — common on independent villas with sloping roofs and on industrial sheds — the priority is checking rust, particularly at sheet overlaps, and confirming that the existing self-drilling fasteners have not loosened. Damaged sheets must be replaced before installation. Mounting is via L-foot brackets that grip the sheet ridge or via clamp-on rails, both designed not to puncture new holes in the sheet.
For a Mangalore tile roof, direct solar mounting is rarely viable. The tiles are brittle, the timber battens supporting them have variable load capacity, and walking on the roof during installation breaks tiles. Most installations on tile roofs use either a ballasted ground-mount adjacent to the building, a structural steel frame above the tile profile, or a tile-replacement system where tiles in the array footprint are removed and replaced with hook brackets. Plan an additional ₹15,000–₹30,000 budget for these alternate mounts. The solar mounting structures guide covers each option in depth.
Roof type also affects the design of the system — orientation flexibility, tilt angle, and panel layout all change. The home solar design guide walks through how installers translate roof type and area into a system layout.
Pre-Installation Timeline — What to Do 4 Weeks vs 1 Week Before
The work compresses naturally into a four-week window. Doing items out of order — for example, sweeping the roof before injecting cracks — creates rework. The sequence below is what our project coordinators hand the homeowner at the survey stage.
| Week | Focus | Tasks | Cost band |
|---|---|---|---|
| Week −4 | Structural & leaks | Structural opinion, water test, mark damp patches | ₹2,000–₹6,000 |
| Week −3 | Civil repair | Crack injection, waterproofing top-up | ₹4,000–₹10,000 |
| Week −2 | Drainage & obstructions | De-choke khurras, remove loose items, antenna removal | ₹500–₹2,000 |
| Week −1 | Electrical & access | Electrician pre-visit, DB check, scaffold route clear | ₹500–₹1,500 |
| Day −1 | Final sweep | Roof sweep, photograph, neighbour NOC, water and shade off | Negligible |
In Week −4, the goal is diagnosis. Get the structural opinion, run the water test, mark every damp patch. Do not start fixing anything yet — you need the full picture first, because crack injection on a slab with a structural concern is wasted money.
In Week −3, the civil work happens. Crack injection, waterproofing top-up, any masonry repair on parapets. This is the biggest single cost in the prep budget and the longest cure time — give the new waterproof layer at least 10–14 days to fully cure before solar drilling starts.
In Week −2, drainage and obstruction work. De-choke khurras, remove the old TV dish, take down the temporary tarp shed from the previous repair. By the end of this week, the roof should be a clean, dry, level working surface.
In Week −1, electrical and access. Electrician confirms DB readiness, earthing, and conduit path. Walk the scaffolding route with the building secretary or family members so everyone knows installation day will involve a corridor for material movement.
On Day −1 (the day before installation), do a final dry sweep, take handover photos, collect the neighbour NOC, and ensure the water connection on the roof is shut off and the rooftop water tank (if any) is full so the installer’s team has water for cleaning panels at sign-off.
Free pre-installation survey. Heaven Green Energy conducts a free site visit covering all 8 checklist points before you commit to a system size. We hand you the prep schedule, the cost band, and the realistic install date. Get your free survey →
Common Defects and Their Repair Costs
These are the defects we see most often during pre-installation surveys, with current (2026) Indian repair price bands. Costs vary by city and contractor, but the bands hold for tier-1 and tier-2 metros.
| Defect | Diagnosis | Repair method | Typical cost |
|---|---|---|---|
| Hairline crack in slab | Visible crack, sometimes weeping | Epoxy / PU grout injection | ₹400–₹800 per running metre |
| Damp patch on ceiling below | Active seepage under crack | Crack injection + top-coat patch | ₹2,000–₹4,000 per patch |
| Waterproofing membrane past life | Bubbling, peeling, brittle to touch | Brush-coat acrylic refresh | ₹12–₹18 per sq ft |
| Choked khurra | Standing water after rain | Plumber de-choke, fresh grating | ₹300–₹500 per outlet |
| Rusted metal sheet lap | Brown streak, fastener corrosion | Sheet replacement, new screws | ₹250–₹450 per sq ft |
| Broken Mangalore tile in array zone | Visible crack or chip | Tile replacement | ₹50–₹120 per tile |
| Insufficient DB space | No spare two-pole slot | Sub-DB add-on for solar | ₹2,500–₹5,000 |
| Earth pit missing or open-circuit | Continuity test fails | Fresh IS 3043 earth pit | ₹3,500–₹6,000 |
| AC outdoor unit on south face | Visible obstruction in array zone | Relocation by AC technician | ₹1,500–₹3,500 |
| Water tank shading the array | Shadow mapping during 9 a.m.–4 p.m. | Tank shift or raise stand | ₹2,000–₹6,000 |
For most homes, the prep bill lands at ₹3,000–₹15,000 — driven primarily by waterproofing refresh and a couple of khurra de-chokes. Older homes that need crack injection and a structural opinion can run to ₹20,000–₹30,000, which is still a fraction of the cost of post-install rework.
Two cost notes worth remembering. First, prices vary 20–30% between cities — Mumbai and Bengaluru civil rates run higher than Jaipur or Indore, mostly because labour costs and material handling differ. Get two quotes before signing for any work over ₹5,000. Second, the band quoted assumes a residential 1,000–1,500 sq ft roof. Larger roofs scale roughly linearly for waterproofing and crack work, but fixed-cost items (structural opinion, earth pit, DB upgrade) stay roughly constant — so a 2,500 sq ft roof prep usually costs only 30–40% more than a 1,200 sq ft roof, not double.
For homeowners weighing whether to bundle prep into the installer’s contract or hire trades separately, the math usually favours separation — installers add a 15–25% margin on civil sub-contracts. Direct hire of a local mason and electrician, with the installer’s prep brief in hand, typically saves ₹2,000–₹4,000 on a standard residential job. The exception is when your installer has a long-standing trade relationship and quotes the civil portion at cost, which is occasionally the case in tier-2 cities.
Common Roof-Prep Mistakes That Delay Installation
Across the residential installations we coordinated in 2024–25, the same five prep mistakes delayed roughly 8 in 10 jobs that ran beyond the planned window. Each is small. Each is preventable.
-
1
Skipping the structural opinion on older slabs. A ₹2,000 written opinion from a civil engineer protects the 25-year warranty. Homeowners often skip it for slabs they "know are fine" — and the installer then refuses to mount until the opinion is on file.
-
2
Doing waterproofing the same week as installation. Fresh APP or acrylic needs 10–14 days to fully cure. Drilling mounting feet into uncured membrane creates the exact leak point you were trying to avoid.
-
3
Not relocating the AC outdoor unit or water tank. A south-facing AC compressor or a tank casting a 4-metre shadow can sit unnoticed for years. On install day it suddenly blocks 20% of the array. Relocate them in Week −2, not on Day 0.
-
4
Assuming the existing earthing is adequate. Most pre-2015 residential earth pits do not pass an IS 3043 continuity check. The installer's electrician will flag this on Day 1. Get it tested and replaced in Week −1.
-
5
No written neighbour NOC for shared-wall homes. A verbal "okay" becomes a stop-work argument on Day 2 when the drilling starts. A one-line signed note in advance closes the issue.
-
6
Leaving choked khurras until after install. Once the array is up, you cannot reach the khurra easily. Clear all drainage outlets the week before mounting starts.
Watch out
Never let an installer convince you to "patch the leak after we mount the panels". Mounting feet drilled into compromised waterproofing void the structural warranty and create permanent ingress points that age the slab faster than the panels age. If the installer is willing to skip prep, the installer is not the right partner. Walk away and find one who insists on the prep work first.
DIY Prep vs Hiring a Roofer
Most of the prep work is within DIY (do-it-yourself) range for a handy homeowner — sweeping, de-choking khurras, photographing damp patches, taking out an old TV antenna. The civil interventions — crack injection, waterproofing refresh, structural opinion — are not. The honest split looks like this.
- + Saves ₹3,000–₹5,000 on basic clearance work
- + You know the roof's history better than any contractor
- + Builds familiarity with the system you'll own 25 years
- − Civil work (crack injection, waterproofing) needs trade skill
- − Structural opinion must come from a qualified engineer
- − Roof-edge work without a harness is genuinely dangerous
- + Trade skill on injection, membrane, fastener replacement
- + Written workmanship warranty on the prep work
- + Faster completion in 1 week vs 3 weeks DIY pace
- − Adds ₹8,000–₹15,000 to the prep budget
- − Quality varies widely outside large cities
- − Coordination overhead with the solar installer's schedule
Verdict. Hybrid is best. Do the clearance, sweep, drainage check, and photo documentation yourself. Hire a roofer for crack injection, waterproofing refresh, and any fastener or sheet replacement. The combined approach typically costs ₹6,000–₹12,000 for the average home and finishes in two calendar weeks. Pure DIY saves the least money for the most risk; pure outsourcing over-spends on tasks that need no trade skill.
A practical rule for the split — anything that needs ladder work below 3 metres, a broom, a moisture meter, or a mobile camera is DIY. Anything that needs a putty knife on cured concrete, an injection gun, a roller for membrane application, or a torch for APP sealing is trade work. The financial gap between the two columns is about ₹5,000–₹8,000 for a standard residential job, and the DIY effort saves roughly 8–12 hours of personal time across the four-week prep window — much of it pleasant rooftop work in the cooler morning hours.
How Heaven Green Energy Helps with Pre-Installation Survey
Heaven Green Energy bundles the 8-point checklist into a free pre-installation survey that we run before quoting any residential system. The team visits the roof, runs the structural read, marks the array footprint, photographs shading sources, and hands you a written prep schedule with cost bands by line item.
Across the residential surveys we ran in 2024–25, the pre-survey caught ~92% of issues that would otherwise have surfaced on install day — undersized DB spaces, choked khurras, ageing waterproofing, AC units in the array footprint. The remaining 8% are issues that genuinely cannot be detected until scaffolding is up, and those are flagged on Day 1 with a fix plan.
What our pre-installation service covers:
- 8-point checklist run on site, with chalk-marking of every action item.
- Written structural opinion sourced through our partner civil engineers (₹2,000–₹4,000 cost band, transparent to the homeowner).
- Coordination with your preferred roofer, or sourcing one from our trade panel.
- Shading study using a sun-path app, capturing the 9 a.m. to 4 p.m. envelope across the full year.
- DB and earthing pre-check by our electrician, with a written fix list.
- Final go/no-go sign-off before installation team mobilises, so nobody arrives to a roof that is not ready.
Explore the services that match where you are:
- Residential Solar — 1–10 kW rooftop systems with pre-installation survey, prep coordination, and PM Suryaghar subsidy handling.
- Solar Calculator — quick sizing and subsidy estimate against your monthly bill.
- Contact Heaven Green — book a free 45-minute on-site survey.
For step-by-step inspection guidance the day before the installer arrives, read the roof inspection guide.
The survey itself runs 45–60 minutes on site and is followed by a written report we email within 48 hours. The report contains the prep schedule, the cost band against every line item, a 9 a.m.–4 p.m. shading map of the planned array footprint, a marked photograph of the proposed mounting points, and a fix list with priority tags. Homeowners use the report to compare quotes from other installers, to brief their own civil contractor, or simply to plan the four-week window around family schedules. There is no obligation to install with us after the survey — the report is yours to use however you choose.
Frequently Asked Questions
How long before solar installation should I start preparing my roof?
Start 4 weeks before the scheduled installation date. Week −4 is for diagnosis (structural opinion, water test, damp-patch mapping). Week −3 is for civil work (crack injection, waterproofing refresh) which needs 10–14 days to cure. Week −2 handles drainage and obstruction removal. Week −1 covers electrical readiness and scaffolding access. Compressing this into 1 week creates rework and almost always delays the installation by a similar margin.
What is the typical cost of pre-installation roof preparation in India in 2026?
Most residential homes spend ₹3,000–₹15,000 on prep, driven mainly by waterproofing top-up (₹8,000–₹14,000 on a 1,000 sq ft roof) and minor civil repair. Older homes needing crack injection and a structural opinion can spend ₹20,000–₹30,000. Metal-sheet roofs with rusted laps and Mangalore tile roofs requiring alternate mounts can push the budget to ₹25,000–₹40,000. The prep cost is almost always less than 5% of the total solar system cost.
Do I need a structural engineer’s opinion before installing solar on my RCC roof?
For RCC slabs less than 15 years old, built to IS 456 code with M20 or higher concrete and at least 110 millimetres thick, a written structural opinion is recommended but not always insisted on by installers. For slabs older than 15 years, or with visible cracks, spalling, or sagging, a written opinion from a qualified civil engineer is mandatory and protects both the installer’s warranty and your home insurance. The opinion costs ₹2,000–₹4,000.
How do I check for roof leaks before solar installation?
Run a deliberate water test. Block one khurra, flood a 2-metre-square section of the roof with 5–10 centimetres of standing water for 4–6 hours, and inspect the ceiling directly below for damp patches, drips, or discoloration. Mark every damp patch with chalk. Repeat for each roof zone. For a faster qualitative check, use a moisture meter at suspect points or simply review the ceiling below after the next sustained rain — any visible staining is an active leak path.
Can I install solar on a roof with a leak if I plan to fix it later?
No. Mounting feet drilled through a compromised waterproof layer create permanent ingress points and concentrate water at the worst possible location — under a panel where you cannot reach the leak. Most installers will refuse to mount on a leaking roof, and those who agree will void the structural warranty. Fix every leak in Week −4 to Week −3 of the prep timeline, allow 10–14 days for cure, then run a second water test to confirm before installation.
What roof types are most difficult to prepare for solar in India?
Mangalore tile and other clay-tile roofs are the most difficult. The tiles are brittle, the supporting battens have variable load capacity, and walking on the roof during installation tends to break tiles. Most tile-roof installations use either a structural steel frame above the tile profile, a tile-replacement system with hook brackets, or an adjacent ground-mount. Plan ₹15,000–₹30,000 extra over a comparable RCC installation. Old metal roofs with widespread rust are the second-hardest category and may require partial sheet replacement before mounting.
Does my earthing need to be redone for solar installation?
Often yes. The IS 3043 earthing standard requires a verified low-resistance earth path for the inverter chassis, array frame, and AC output. Most pre-2015 residential earth pits do not pass an IS 3043 continuity check. The installer’s electrician tests this on Day 1; if it fails, you’ll need a fresh earth pit costing ₹3,500–₹6,000 plus a half-day delay. Get the test done in Week −1 of the prep timeline to avoid the delay.
What happens if my roof is not prepared when the installer arrives?
The installer team will either stand down for the day (you pay the visit charge) or document the issues and reschedule once prep is complete. Common reasons for stand-down: active leaks, missing structural opinion on old slabs, blocked array zone, inadequate DB space, failed earthing check, no neighbour NOC for shared walls. Each issue typically adds 3–10 days to the rescheduled date. Pre-installation prep is the single highest-return investment a homeowner makes in solar.