ALMM List-II Exemption Window Extended to Dec 2026

MNRE's ALMM List-II exemption for net metering and open access projects runs till 31 December 2026 — commission before then to skip the cell rule.

ALMM List-II Exemption Window Extended to Dec 2026

The ALMM List-II exemption just got a lifeline that every factory owner, warehouse operator, and open access buyer in India needs to understand this week. On 18 July 2026, the Ministry of New and Renewable Energy (MNRE) issued Office Memorandum No. 283/53/2026-GRID SOLAR, extending the exemption from ALMM List-II (the Approved List of Models and Manufacturers for solar PV cells) for net metering projects and open access renewable energy projects right up to 31 December 2026. The previous cut-off was 31 May 2026, so this is a five-month runway that reopens panel choice for commercial and industrial solar. If you commission your plant on or before the deadline, you can still use modules built with cells that are not yet on ALMM List-II — which usually means wider availability and lower cost. Miss it, and full List-II compliance becomes mandatory from 1 January 2027.

Direct answer. MNRE’s 18 July 2026 order extends the ALMM List-II (solar PV cells) exemption for net metering and open access renewable projects to 31 December 2026 — five months beyond the earlier 31 May 2026 cut-off. Projects commissioned by that date may use non-List-II cells; those commissioned in 2027 must comply. Heaven Green Energy is helping C&I clients commission before the deadline.

📄 MNRE Office Memorandum No. 283/53/2026-GRID SOLAR

The original order, dated 18 July 2026 — download the official PDF.

⬇ Download PDF

The catch is in one word: commissioned. Not booked, not delivered, not half-installed — commissioned and synced to the grid. This guide breaks down exactly what the order says, who it covers, and how to plan your timeline so the exemption actually applies to you.

What does the MNRE ALMM List-II exemption extension actually say?

The order provides a limited window — not a permanent removal — of the ALMM List-II requirement for two specific project types. In plain terms, MNRE has decided there will be no blanket extension of ALMM List-II for solar power projects generally, but net metering and open access renewable projects get a special dispensation to commission with an exemption from the List-II (solar PV cell) rule until 31 December 2026.

To understand why this matters, you need the ALMM basics. ALMM is India’s quality-and-domestic-manufacturing gatekeeper. List-I covers finished solar modules; List-II covers the solar cells inside those modules. From 1 June 2026, MNRE’s baseline rule required that modules used in government-linked, net metering, and open access projects source their cells only from List-II-approved Indian manufacturers. This new memorandum supersedes a chain of earlier orders (dated 25 May, 8 June, 15 June, and 23 June 2026) and settles the timeline at 31 December 2026 for these two categories.

The stated reason is a smooth transition. MNRE says the decision followed detailed deliberations with solar-industry stakeholders, giving module makers more time to shift their cell sourcing to List-II suppliers as domestic cell capacity scales up. You can read the order itself in the official MNRE Office Memorandum (PDF), find it listed under MNRE Current Notices, and read the broader policy on the MNRE ALMM page. For a homeowner-level primer on why domestic-content rules exist at all, see our explainer on DCR vs non-DCR solar panels.

📘 Regulation note

This exemption applies only to the ALMM List-II (cell) requirement. ALMM List-I (module) enlistment stays mandatory. Your panels must still be from a List-I-approved model — only the origin of the cells inside them is relaxed until 31 December 2026.

ALMM List-I vs List-II: modules versus cells

The single most common confusion is treating ALMM as one rule. It is two separate lists that regulate two separate parts of the panel. Getting this distinction right decides whether your project qualifies for the exemption.

DimensionALMM List-IALMM List-II
CoversFinished solar PV modules (panels)Solar PV cells inside the modules
First issued10 March 202131 July 2025
Status for net metering / open accessMandatory — no exemptionExempt till 31 December 2026 (this order)
What it controlsWhich panel models are grid-approvedWhether the cells are Indian-made and approved
Analogous conceptApproved product listA cell-level domestic content requirement

The table makes the point: List-I never went away. What the 18 July order touches is only List-II. A module can sit on List-I while using imported or not-yet-List-II cells — and for net metering and open access projects, that combination is legal to commission until the year-end deadline. This is close in spirit to the older non-DCR allowance, though the two schemes are legally distinct.

MNRE first published the ALMM List-II for solar PV cells on 31 July 2025, and has revised it several times since. You can verify the underlying notice on the MNRE List-II publication page. If you are choosing panels for a C&I roof or ground-mount, our guide on how to choose solar modules walks through the specs that matter beyond ALMM status.

Who does the December 2026 exemption cover?

Two project categories, named explicitly in the order: net metering projects and open access renewable energy projects. If your project is neither, this window does not apply to you, and List-II compliance is already the default from 1 June 2026.

Net metering is the arrangement where a rooftop or on-site solar plant feeds surplus power back to the grid and the consumer is billed on the net of import minus export. It is the backbone of most factory, warehouse, hospital, and commercial rooftop projects. Our detailed breakdown of net metering in India covers the meter, the credits, and the DISCOM (electricity distribution company) process.

Open access lets a large consumer buy renewable power from a third-party generator through the grid, paying wheeling and other charges. It is common for energy-intensive industries that cannot host a large enough plant on their own premises. If you procure solar through a group captive or third-party open access model, this exemption directly affects your commissioning strategy.

💡 Fast tip

Ground-mounted C&I plants that sell or wheel power under open access, and factory rooftops on net metering, are the two clear winners here. A quick eligibility check with your EPC now saves a scramble in December.

Here is how the ALMM List-II timeline has moved for these categories, so you can see exactly where the new deadline sits.

DateWhat happenedSource
31 Jul 2025First ALMM List-II for solar PV cells publishedMNRE, 2025
1 Jun 2026List-II cell sourcing becomes the baseline requirementMNRE, 2024 order
31 May 2026Earlier exemption window for net metering / open access closesMNRE, 2026
18 Jul 2026Exemption reopened and extended to year-endMNRE O.M. 283/53/2026
31 Dec 2026Final commissioning deadline for the exemptionMNRE, 2026
1 Jan 2027Full List-II compliance mandatory for these projectsMNRE, 2026

One important clarity from the order: any reference to the superseded memoranda that appears in other MNRE orders on ALMM is to be read as amended in line with this decision. So the 31 December 2026 date is now the single, controlling deadline for these categories — earlier dates in older circulars no longer bind you.

The numbers behind the extension

Why did MNRE blink? Because the arithmetic of domestic cell supply did not add up in time. India’s approved cell capacity is still far below its module capacity, and forcing every project onto List-II cells overnight would have stranded projects and raised prices.

31 Dec 2026
New List-II exemption deadline
MNRE O.M. 283/53/2026, July 2026
~30.3 GW
ALMM List-II cell capacity
7th revision, as of Apr 2026 — MNRE
~193 GW
India module manufacturing capacity
Industry estimate, 2026
31 Jul 2025
First List-II published
MNRE notice, 2025

The gap is stark: roughly 30 GW of approved cell capacity against nearly 193 GW of module capacity (industry estimates) means cell supply is the bottleneck. Policy research bodies have flagged this mismatch — the CEEW analysis on unlocking solar manufacturing explains why cell and wafer capacity lags module lines. MNRE’s own amendment history, summarised in this PIB press release on the ALMM Order, shows the government sequencing List-I, then List-II, and eventually List-III for wafers and ingots in 2028.

For an industry buyer, the takeaway is practical, not political. Until domestic cell lines catch up, the exemption keeps competitively priced modules on the table. That is real money on a large ground-mount job — and the reason smart operators are moving now. If you want to see why the timing favours acting rather than waiting, read why delaying solar costs industries more.

What “commission before 31 December 2026” means for your project

The word doing all the work in this order is commissioned. MNRE does not reward you for signing a contract or receiving panels in 2026 — it rewards a plant that is fully installed, inspected, metered, and synchronised to the grid on or before 31 December 2026. Here is the sequence your EPC must complete inside the window.

  1. Finalise design and DISCOM application — lock the system size, single-line diagram, and load sanction; file the net metering or open access application with your DISCOM early, because feasibility approval alone can take around 7–15 working days, and timelines vary by state and DISCOM.
  2. Procure ALMM List-I modules — select grid-approved panels; under the exemption, their cells need not be on List-II, which widens supply. Confirm the exact model appears on the current List-I.
  3. Install the plant — mounting structure, modules, inverters, DCDB/ACDB, cabling, and earthing complete and tested.
  4. Pass DISCOM inspection — the DISCOM verifies the installation against the sanctioned design; book this slot weeks ahead, as December is a rush month.
  5. Commission and synchronise — the bi-directional or ABT meter is installed, the plant is energised, and the commissioning certificate is issued. This date — not the order date — is what counts.

Work backwards from 31 December. Inspection and meter installation queues get crowded in Q4, so a project that starts procurement in October is cutting it fine. A realistic C&I ground-mount or large rooftop needs its build to begin well before then to clear commissioning comfortably.

Get a free site visit. Our engineer visits in 24 hours, sizes your plant against the December deadline, and sends a custom proposal in 48 hours — no cost, no obligation. Get your free quote →

The Heaven Green ALMM Deadline Readiness Test

Across our installations we have learned that missed deadlines are rarely about panels — they are about paperwork and sequencing. So we use a simple five-check test to tell a client, in one conversation, whether a 31 December 2026 commissioning is realistic. Score one point per “yes”; four or five means go, two or three means move fast, zero or one means the exemption is likely out of reach.

1
Category fit
Is it net metering or open access? If not, the window doesn't apply.
2
DISCOM filed
Is the net metering / open access application already submitted?
3
Panel secured
Are List-I modules confirmed with a firm delivery date?
4
Site ready
Is the roof or land structurally cleared for install to start?
5
Inspection slot
Can DISCOM inspection be booked inside the Q4 window?

The value of the test is honesty. It stops a buyer from ordering panels in November on the assumption that installation is the hard part, when in reality the DISCOM inspection and meter queue is what sinks December deadlines. Run this test against your own project today. If you are unsure of your category or timeline, our industrial solar EPC team can score it with you on a single call.

Red flags that can cost you the exemption

The exemption is generous, but it is unforgiving on process. These are the mistakes we see most often — each one can push your commissioning into 2027 and force full List-II compliance.

  1. 1
    Treating "installed" as "commissioned" — the plant must be inspected, metered, and synchronised. Panels on the roof do not count.
  2. 2
    Filing the DISCOM application late — feasibility approval and inspection have their own queues; a December filing rarely clears in time.
  3. 3
    Using a module not on ALMM List-I — the exemption relaxes List-II cells only. A non-List-I panel is still ineligible.
  4. 4
    Assuming a further extension — MNRE has been explicit: no blanket extension. Projects commissioned in 2027 must comply with List-II.

⚠️ Watch out

Case-by-case relief for near-complete projects is examined by an MNRE expert committee through the national DCR portal run by NISE, but that is a fallback — not a substitute for commissioning on time. Treat 31 December 2026 as a hard wall.

If your DISCOM process feels opaque, our state-specific guide to Gujarat solar policy shows how the empanelled-vendor and net metering steps flow in practice across UGVCL, DGVCL, MGVCL, and PGVCL.

Non-List-II cells vs List-II cells: what it means for cost and panel choice

Should you rush to use the exemption, or simply build to full List-II compliance now? The honest answer depends on your timeline and budget. Here is the trade-off, side by side.

✓ Commission under the exemption
  • Wider module availability — not limited to List-II-cell stock
  • Often lower per-watt cost while cell supply is tight
  • Faster procurement, shorter lead times
  • Locks in today's pricing before 2027 compliance
✗ Watch-outs
  • Hard 31 December 2026 commissioning wall
  • Q4 DISCOM inspection queues get crowded
  • No benefit if your category isn't net metering / open access
  • Future expansions may still need List-II cells

Verdict. If you already have a live net metering or open access project that can realistically commission by year-end, use the window — it widens panel choice and protects your cost. If your project cannot clear DISCOM inspection before December, plan for full List-II compliance instead of gambling on a queue. For anything on the fence, the deciding factor is your DISCOM timeline, not your panel order.

Panel quality does not drop because of where the cells sit on a list — a strong module is a strong module. What changes is your sourcing flexibility. If you want to weigh actual panel economics for your load, our solar calculator sizes the system and estimates savings in about 60 seconds.

How Heaven Green Energy Helps

Heaven Green Energy has completed 10,000+ solar installations across 25+ cities, and our teams know the difference between a plant that is installed and one that is commissioned on the record. For this deadline specifically, we manage the whole path — DISCOM filing, ALMM List-I module sourcing, installation, inspection scheduling, and commissioning — so your net metering or open access project clears the 31 December 2026 window with room to spare. We plan Q4 projects backwards from the inspection queue, not forwards from the purchase order, which is the single biggest reason our deadline projects land on time.

  • Industrial Solar EPC — 100 kW+ turnkey ground-mount and factory-roof plants with commissioning managed against policy deadlines.
  • Commercial Solar — rooftop and open access systems for offices, warehouses, and hospitals with net metering handled end-to-end.
  • Turnkey Solar EPC — design, procurement, and grid synchronisation under one accountable contract.
  • Solar Calculator — size your plant and see savings before you commit, in 60 seconds.

Sources and official references

Every date and figure in this article is drawn from primary government documents and high-authority reporting. Verify them yourself:

Frequently Asked Questions

What is the new ALMM List-II exemption deadline?

MNRE’s Office Memorandum dated 18 July 2026 sets 31 December 2026 as the deadline for net metering and open access renewable energy projects to commission with an exemption from the ALMM List-II (solar PV cell) requirement. The earlier window ended on 31 May 2026, so this is a five-month extension. Projects commissioned on or before 31 December 2026 can use modules whose cells are not on List-II; projects commissioned from 1 January 2027 must comply fully with List-II.

Does this exemption apply to all solar projects?

No. The exemption applies only to two categories named in the order: net metering projects and open access renewable energy projects. MNRE has explicitly stated there is no blanket extension of ALMM List-II for solar power projects generally. Government-linked utility projects outside these two categories remain subject to their own timelines. If your project is a standard net metering rooftop or an open access plant, you qualify; otherwise, List-II compliance is already the default from 1 June 2026.

What is the difference between ALMM List-I and List-II?

ALMM List-I is the Approved List of Models and Manufacturers for finished solar modules (panels), first issued in March 2021. ALMM List-II covers the solar PV cells inside those modules, first published on 31 July 2025. From 1 June 2026, modules in covered projects had to use List-II cells — but this order defers the List-II cell rule for net metering and open access projects to 31 December 2026. List-I compliance for the module itself is unchanged and still mandatory.

What does “commissioned” mean for the deadline?

Commissioned means the plant is fully installed, inspected by the DISCOM, fitted with the appropriate meter, and synchronised to the grid — with a commissioning certificate issued on or before 31 December 2026. It does not mean the panels are ordered, delivered, or merely mounted. Because the commissioning date is what counts, your EPC should work backwards from the DISCOM inspection queue, which gets crowded in the final quarter of the year.

Can I still use non-DCR or imported-cell panels?

For net metering and open access projects commissioned by 31 December 2026, yes — the exemption relaxes the requirement that cells come from ALMM List-II, so modules built with non-List-II cells (often imported cells) are permitted. The module itself must still be on ALMM List-I. See our guide on DCR vs non-DCR solar panels for how the cell-origin rules translate into panel choice and cost.

Why did MNRE extend the exemption?

Domestic solar cell capacity has not scaled fast enough. India’s ALMM List-II approved cell capacity is around 30 GW, while module manufacturing capacity is roughly 193 GW — so cell supply is the bottleneck. Forcing every project onto List-II cells immediately risked stranding projects and raising prices. MNRE extended the window after deliberations with industry to allow a smoother transition as more domestic cell lines get approved and come online.

What happens to projects commissioned after 31 December 2026?

They must comply fully with the ALMM List-II provisions. From 1 January 2027, net metering and open access projects will be required to use modules whose cells are sourced from ALMM List-II-approved Indian manufacturers. MNRE has stated there is no blanket extension beyond this date, so buyers should not plan on a further reprieve. If your timeline slips into 2027, budget and design for List-II-compliant modules from the outset.

How can Heaven Green Energy help me meet the deadline?

We manage the full commissioning path for net metering and open access projects — DISCOM application, ALMM List-I module procurement, installation, inspection scheduling, and grid synchronisation — planned backwards from the year-end inspection queue. Our engineers run a free site assessment within 24 hours and send a custom proposal in 48 hours, so you know quickly whether a 31 December 2026 commissioning is realistic for your site. Call +91 63904 05060 or request a callback to start.

Written by
Keyur Rakholiya

Co-Founder of Heaven Green Energy. Oversees engineering, product, and the Qbits inverter line — from cell-to-module design to on-site commissioning of MW-scale plants.

Ready to Go Solar?

Turn this knowledge
into real savings.

Get a free site assessment and custom savings proposal, no cost, no commitment. Our engineers will visit your location within 24 hours.

Call WhatsApp