Sources checked: 23 November 2026. Utility rules and offer terms can change; check the current documents for your site before relying on a proposal.
A commercial solar proposal is ready to sign when you can tell which electricity account it serves, what the contractor will build, what it will cost, who owns each risk, and how the result will be measured. A headline system size and a projected saving are not enough. For a shop, office, hotel, school or mixed-use building, the questions are different from a household rooftop quote: business hours, multiple meters, tenancy, tax treatment, roof repairs, electrical shutdowns and responsibility for operating the plant can decide whether the model is credible.
Ask every bidder for the same site information and the same response fields. The US Department of Energy’s commercial-solar provider-selection guide recommends setting evaluation criteria before seeking bids. Its US legal terms do not govern a Gujarat project, but the procurement method is useful: define the job once, then compare like-for-like answers. India’s SECI rooftop tender material likewise shows how formal buyers separate project scope and bid documents. A private business needs a shorter version of that discipline, not a government-sized tender.
1. Which meter and tariff are we solving for?
Begin with the consumer number, distribution licensee, tariff category and billing period. A business can have separate meters for a ground-floor shop, office floors, lift and common areas, air-conditioning plant or another leased unit. A proposal that adds all those bills and then assumes one rooftop system can offset all of them has skipped the connection arrangement. Put the exact meter or approved group arrangement on the first page of the proposal.
Ask for 12 consecutive bills, not only the highest month. Write down imported kWh, maximum demand where relevant, tariff category, time-of-use registers, fixed and demand charges, duties and adjustments. A restaurant’s lunch and evening demand pattern differs from a daytime office. A warehouse may have little daytime load despite a large roof. A school may close for weeks while the roof keeps generating. The project’s value depends on the overlap between generation and consumption, as well as the legal settlement arrangement.
For Gujarat projects, GERC’s distributed renewable energy regulations notified on 30 October 2026 set the framework for net metering, net billing, gross metering and other arrangements within their scope. The regulation is not a substitute for the licensee’s approved procedure or project approval. Ask the bidder to state which arrangement it has modelled, why the account is eligible, and what it assumes about exported energy. A spreadsheet that values every generated unit at the retail import rate may be wrong for your usage pattern and mechanism.
| Proposal field | The answer to request | Why it matters |
|---|---|---|
| Utility account | Named consumer number and tariff category | Prevents modelling the wrong connection |
| Baseline | Bill period, 12-month import and demand, time-of-use data if available | Shows seasonality instead of a single selected month |
| Metering arrangement | Relevant GERC clause and proposed licensee route | Determines treatment of export and import |
| Occupancy schedule | Hours, weekends and closure periods | Determines how much solar is likely to be used on site |
| Future change | Expansion, new tenant or load relocation | Tests whether the assumed load will persist |
This is a request table, not a sample client result. A bidder should use your actual documents and explain any missing data.
2. What exactly is being quoted?
Ask for DC module capacity in kWp and AC inverter capacity in kW, both labelled. A 100 kWp module array and an 80 kW inverter are not two competing descriptions of a “100 kW system”; they are different electrical quantities. The proposal should name module and inverter make and model, quantity, mounting approach, cable and protection scope, monitoring, meter work, and the boundary with the building’s existing distribution board. If the model can change after signature, the contract should state how substitution is approved and priced.
Do not accept “premium modules” or “Tier 1 equipment” as a technical specification. Ask for current model datasheets and certification evidence for the exact offered SKU. A warranty label does not establish who will pay for removal, transport, labour or replacement if the equipment fails. Name the warrantor, start date, transferability, exclusions and claim process. The brand’s general brochure may not describe the specific component on your bill of materials.
The scope boundary deserves its own drawing. Who checks structural adequacy? Who repairs a weak roof or waterproofing? Who provides safe access and fall protection? Who approves the inverter location and ventilation? Who modifies the electrical panel and pays for a larger meter cabinet or transformer work if required? Check the applicable CEA electrical-safety regulations when specifying DC circuits, earthing, isolation and protection. A rooftop is an electrical installation on an occupied building, not merely a set of panels on empty space.
3. Has anyone actually checked the roof?
A photo and a pin on a satellite map are useful for an initial conversation but cannot establish roof capacity or condition. Ask what the structural engineer will inspect, what records the owner must provide, whether roof repairs are included, and how the mounting transfers wind and dead load to the building. On a metal shed, sheet condition and clamp or fastener method matter. On an RCC terrace, waterproofing, drainage and service access matter. A roof with multiple air-conditioning units, skylights or fire exits needs a marked obstruction and access plan.
If the business is a tenant, ask who controls the roof and who can authorise installation, access, repair and removal. The GERC 2026 regulation requires the system owner to own, lease, lawfully possess or otherwise have valid legal authority to install and operate at the location. That regulatory wording does not replace a clear landlord agreement. The contract should cover what happens when the lease ends, the roof is replaced, or the building is sold.
Ask how the team will work above occupied rooms. Drilling, lifts, material storage and electrical tie-in can affect tenants or customers. “No disruption” cannot be promised without a work method and a shutdown plan. If a contractor proposes to place modules over a fragile rooflight or block maintenance access to a tank, vent or fire equipment, request a revised layout before price negotiations.
4. How was generation and bill impact calculated?
The generation model should state weather data source, roof tilt and orientation, shading, DC-to-AC ratio, loss factors and annual degradation assumption. More importantly, the bill model should identify self-consumed generation, exported generation and grid import after solar separately. A business owner cannot judge value from annual kWh alone. The owner needs to see which hours the building uses power and which hours the array produces it.
Ask the bidder to provide at least two cases: a base case using current documented operation, and a downside case with lower daytime load or lower generation. If an office expects a tenant change, model that change explicitly. If a school closes for holidays, do not annualise a term-time weekday. Avoid a “guaranteed payback” number built from an unsupported electricity-price escalation or a subsidy that does not apply to commercial accounts. The MNRE PM Surya Ghar guidelines exclude non-residential consumers from the central residential CFA; do not insert that grant into a shop or factory calculation.
| Number in a proposal | Unit | What the owner should ask |
|---|---|---|
| Module capacity | kWp DC | Which models, count and wattage make this total? |
| Inverter capacity | kW AC | What export and grid connection limit applies? |
| Annual solar generation | kWh/year | Which weather and loss assumptions produced it? |
| On-site use | kWh/year | What load profile supports this estimate? |
| Export | kWh/year | Which settlement arrangement and rate were used? |
| Bill reduction | ₹/year | Which tariff lines change, and which remain? |
| Project cost | ₹ with tax scope stated | Which exclusions can add cost later? |
The rows deliberately keep units visible. Confusing a kW demand charge with kWh energy units, or annual production with units actually self-used, creates false savings even when the arithmetic in each spreadsheet cell is correct.
5. Which costs and approvals are outside the headline price?
Request a line-item price split for equipment, structure, installation, design, roof work, electrical modification, meter and approval work, monitoring and post-commissioning service. Mark each as included, excluded or provisional. If the roof requires strengthening, ask for an engineering basis and separate price. If the DISCOM requires network or meter work, ask who pays the actual charge. A quotation with an attractive low total and vague exclusions is difficult to compare fairly with a more complete bid.
The bidder should identify the application owner, required drawings and certificates, utility review, any applicable electrical-inspector process, meter testing and commissioning sequence. The GERC regulation includes an activity chart and refers to CEI charging approval whenever applicable; it does not mean every business rooftop follows one universal approval list. Ask the contractor to state what is confirmed for your voltage and capacity, what depends on the authority, and who handles a requested redesign. A useful schedule shows dependencies, not a promised energisation date unsupported by a technical-feasibility approval.
For a GST-registered business, tax treatment belongs in a separate finance review. Ask for the tax invoice structure and the exact classification the EPC intends to use. Input tax credit, depreciation and financing outcomes depend on the buyer and the law applicable at the transaction date. The solar contractor should provide a clear bill of materials and contract scope; a CA should decide the tax treatment. If a proposal presents an after-tax return without naming those assumptions, ask for a pre-tax base case.
6. Who owns performance and maintenance after handover?
The commercial question is not only whether the plant produces on day one. Ask who monitors daily output, how faults are reported, who inspects structure and cables, what cleaning access exists, and how a defective module or inverter is handled. A product warranty is a manufacturer’s obligation under its written terms; an EPC workmanship warranty and an operations contract are different obligations. Put all three on separate lines.
Ask for a handover pack: as-built layout and single-line diagram, equipment serial numbers, datasheets, test and commissioning records, meter and approval documents, monitoring access, warranty papers and emergency isolation instructions. If a facility manager leaves, the next person should still be able to locate the isolators and submit a claim. The US DOE’s photovoltaic procurement lifecycle guidance highlights documentation, testing and inspection as distinct steps; the applicable Indian standards and contract should govern the actual project.
Cleaning is not a fixed monthly promise. A dusty roadside shop, a coastal building and a relatively clean office roof can have different needs. Ask who assesses soiling, what water and access method is safe for the roof, and whether cleaning labour, water and replacement consumables are included. A maintenance plan should name what gets inspected and when, without claiming a guaranteed performance percentage that the contract cannot measure.
7. How can two proposals be compared fairly?
Give the same roof drawings, bills and operating schedule to each EPC. Request the same output fields and mark not provided where a bidder omits one. Normalize the comparison only where the underlying scope is comparable. A price per kWp can be useful after scope is aligned, but it cannot make a quote that excludes roof repair equivalent to one that includes it. Nor does a larger annual-generation claim automatically make a design better if the buyer cannot use or export those units as modelled.
Use a three-column review: documented, assumption, and open issue. Put all claims into one of those columns. For example, “module model ABC123, datasheet dated October 2026” is documented. “Tenant will use the building for 10 years” may be an owner assumption. “Utility will approve 100 kW export” is an open issue until the proper approval exists. The best proposal is the one that lets the owner see these distinctions and assign the remaining work.
| Decision gate | Evidence before signature | Owner of the open item |
|---|---|---|
| Account and load | Bills and operating schedule | Business owner / facility manager |
| Roof rights and structure | Title or lease authority; engineering review scope | Owner / landlord / structural engineer |
| Electrical connection | SLD and proposed tie-in | EPC / electrical engineer |
| Equipment | Exact SKU schedule and datasheets | EPC |
| Utility arrangement | Applicable GERC rule and licensee application | EPC / consumer / DISCOM |
| Economics | Base and downside cases with separate self-use and export | Finance team / EPC |
| Contract | Price, exclusions, milestones and remedies | Procurement / legal team |
This is a buyer checklist, not a finding that a particular vendor is compliant. Where evidence is missing, the right response is to request it or make the contract conditional on a clear review, not fill the cell with confidence.
The short list to send back to the bidder
Before signing, ask: Which meter? Which roof rights? Which exact equipment? Which load profile? Which GERC arrangement? Which structural and electrical reviews? Which costs are excluded? Who obtains approvals? What is the handover pack? Who handles faults? The answers should appear in the written offer or its schedules. If the offer changes after the survey, request a revised version that replaces the old one so the scope and price cannot be confused later.
For an initial review, use Heaven Green Energy’s commercial solar page and request a proposal based on your business’s actual bills and operating hours. Use the business enquiry form to Get a load-based proposal for my business. A separate existing questions to ask a solar installer article is broader; this checklist keeps the business meter, tax review, tenancy and operating load at the centre of the decision.