Quick answer. A factory can start a rooftop-solar discussion with its latest electricity bill and roof photos, but an accurate proposal needs more: roughly twelve consecutive bills, the actual consumer category and contract demand, available interval import data, a current electrical single-line diagram, transformer and board details, a roof drawing or measured survey, and the production calendar. Those records let an EPC test electrical self-use, roof capacity, tie-in, metering and approval rather than guess a system size from the visible roof alone.
You do not have to assemble a perfect engineering archive before speaking to a solar company. You do need to separate what is known from what still requires a survey. The purpose of this list is to help the plant head and finance team request a proposal that can survive technical review and meaningful bid comparison. For a broader scope discussion, see industrial rooftop solar. This document checklist is about the inputs to a proposal, distinct from installation-stage permits and commissioning certificates.
The minimum starter pack
Send the most recent electricity bill for each relevant service connection. It should show the consumer number, utility, tariff code, contracted or sanctioned load, demand, billed energy, taxes or levies, and any time-of-use entries. Where the factory has several meters, label which buildings and production lines each serves. A screenshot with the top and bottom cut off can hide the very fields the model needs. Redact account information only if necessary, and keep the tariff and meter fields readable. The EPC must identify the distribution licensee from the bill, not from the factory’s city alone.
Add a roof plan if one exists, plus safe photographs showing the full roof blocks, sheet condition, skylights, vents, smoke outlets and access. Include the shed’s age, owner and known repair history. A drone image can help with layout, but it cannot establish purlin size, sheet gauge or safe load capacity. If the plant has no roof drawing, tell the EPC that a measured survey and structural review are required. An honest unknown is more useful than a guessed dimension copied into the final quotation.
Finally, share a short production note: daytime and night shifts, weekly closure, seasonal shutdowns, known expansion, major electrical loads and processes that cannot be interrupted. It can be a one-page note, not a polished report. A proposal model based solely on monthly kWh can miss that the roof produces when a line is idle. This starter pack supports a first conversation; it does not by itself authorise a fixed PV capacity or price.
Twelve bills reveal more than a single average
A year of bills shows changes in imports, maximum demand, tariff category, contract demand, time-of-use and fixed charges across seasons and production cycles. It can reveal a large one-off shutdown or a recent increase from new equipment. Ask the EPC to mark unusual months instead of averaging them away. If a factory has recently added a machine or changed shifts, a historical twelve-month average may understate or overstate future daytime demand. The production manager should annotate those changes beside the bills.
The bill also tells the finance team what not to multiply by solar kWh. Energy charges, demand or fixed charges, reactive-energy items, taxes and other levies are separate. Under Gujarat’s current 2026 distributed renewable energy rule, other applicable charges remain payable under net metering. For a non-residential net-metered consumer, export adjustment is capped at 30% of imported energy in the billing period, subject to applicable banking charges; excess export beyond that limit lapses. These are reasons to model direct self-use and the whole bill rather than promise a simple “units generated × headline tariff” saving. GERC Notification 11/2026, Regulations 9.1.5 and 9.1.9.
If the factory is billed by DGVCL, MGVCL, PGVCL or UGVCL, the GERC FY 2026–27 state-owned DISCOM tariff schedule is a current reference. Another licensee may have a different schedule. The EPC should name the exact licensee, consumer category and effective tariff order used; the buyer should not accept a generic Gujarat commercial rate without a bill match. Tariffs can change, so the financial model should state its date and what will be refreshed before signing.
Interval data is the best test of daytime fit
Request 15- or 30-minute meter data if the utility portal, plant energy-management system or meter can export it. The file should include timestamps, units, meter name and enough months to capture ordinary and low-load patterns. If interval data is unavailable, ask for production logs and daily/shift meter readings, then label the uncertainty in the proposal. A single annual yield estimate cannot tell how much solar will be used directly on a Wednesday production shift versus a Sunday closure.
The EPC should overlay an hourly solar model with the factory’s electrical import, accounting for site location, roof orientation, shading, inverter and module assumptions, temperature and other losses. NLR PVWatts is a public example of how location and system inputs affect a PV output estimate; it does not know this factory’s electrical demand. The bid should show expected generation, direct use, grid import after solar, export and any curtailment by period. It should also disclose the weather source and losses. A proposal that offers only annual kWh and a payback year without those inputs is too thin for a working plant.
If the factory has multiple service connections or internal meters, data must be assigned to the correct electrical boundary. A load on a separate utility connection will not necessarily absorb energy from the proposed solar system. Shared rooftops, leases or group arrangements need a written metering and ownership design. Do not merge all monthly electricity units into one spreadsheet without explaining how the meters are connected and what the current GERC mechanism permits.
The electrical single-line diagram decides the tie-in
The SLD should show utility incomer, transformers, main LT or HT panels, bus couplers, DG sets, existing solar if any, capacitor banks and major outgoing feeders. Mark the current utility meter and proposed solar generation meter, bidirectional meter and inverter connection. If the drawing is old, provide the revision date and tell the EPC what has changed. Qualified personnel may need to verify the installed configuration before the connection point is final.
Nameplate photographs or documents for transformers, main breakers and bus ducts help the engineer test whether a proposed tie-in is physically and electrically feasible. Protection settings, fault levels, cable routes and shutdown windows cannot be derived from a roof photo. The proposed SLD should show the point of common coupling and point of solar interconnection separately. A plant with several transformers or an open bus section needs its normal and alternative operating configurations shown.
GERC’s 2026 regulation and model agreement require prescribed generation and bidirectional metering for net metering or net billing, with additional main/check/ABT/Special Energy Meter, CT/PT and communications as specified by the relevant authorities. A commercial proposal should list those as actual or conditional scope after checking the utility’s written procedure. GERC Notification 11/2026, model agreement section 6. A diagram that says only “connect to nearest panel” cannot settle the meter cost or outage plan.
The roof file is more than an area calculation
Useful roof records include architectural or structural drawings, roof sheet profile and thickness, purlin layout, truss details, previous additions, leak repairs and any roof-warranty terms. The EPC should inspect, and a qualified structural engineer should review, the whole load path from modules and brackets to the main frame. Wind uplift, sheet pullout, corrosion and access can make some visible roof area unusable. Mark those excluded zones on a scaled layout rather than counting them in a headline kWp.
Where a shed is leased, provide the lease section on alteration rights and written owner consent if required. A landlord’s permission to use the roof is not the same as structural sign-off. The owner may also require a roof-maker-approved fastening method or restoration terms. These commercial constraints can determine whether a project is feasible even when the roof is strong. Ask who bears roof repairs, future re-roofing and the cost of removing and reinstalling modules if needed.
Photographs should be dated and labelled by roof block. Show high-level context and close-ups of sheet, seams, purlins, vents and existing damage, captured safely. Do not ask untrained staff to climb onto a fragile or inaccessible roof merely to complete an RFQ. An EPC survey can collect measurements under the factory’s permit-to-work system. The proposal should distinguish preliminary remote estimates from on-site verified dimensions.
| Input | What it tells the EPC | Common missing detail |
|---|---|---|
| 12 electricity bills | Tariff, import, demand and seasonal change | Only first page or one unusual month supplied |
| Interval data | Daytime and low-load pattern | Missing timestamps or meter identity |
| Production calendar | Shift, closure and expansion assumptions | New machinery not noted |
| Current SLD | Tie-in and meter boundaries | Old revision omits added transformer or DG |
| Transformer and board data | Ratings and connection feasibility | No nameplate or switchgear access |
| Roof drawings and condition | Area, structure, access and excluded zones | Sheet/purlin details assumed from photos |
| Roof rights | Permission and maintenance responsibilities | Lease consent or warranty position unclear |
Use this as a document tracker. A missing item should have an owner and due date, rather than being quietly replaced by an EPC guess.
What the proposal should return for those inputs
The output should include an assumption register: which records were used, which are provisional, and which require survey or utility confirmation. It should show a roof plan with module layout and excluded areas; proposed DC and AC capacity; module, inverter and mounting models; an energy model with self-use and export; a revised SLD; metering mechanism and responsibility; structural deliverables; approval steps; construction method; outage dependencies; warranty providers; O&M scope; and clear exclusions. A price without these boundaries is hard to compare or hold accountable.
Ask for a sensitivity case if plant operation changes. A factory might shift a line to night, add a daytime compressor or close on more days. The business case should show how such changes affect direct self-use and export, not simply adjust the annual generation by a percentage. Also ask who owns updates when the utility approves a different meter or the structural review reduces usable roof area. Those are normal design developments; a good contract treats them as named decision points.
The document pack can make a tender efficient. Give the same version of bills, roof plan and SLD to every bidder, note the same production assumptions, and ask them to list deviations in one table. If one bidder assumes an LT panel connection and another includes a new transformer, their rupees-per-kWp prices are not directly comparable. The factory should compare scope, system boundary and risks before ranking prices. An RFQ with explicit answers and exclusions protects the plant from a late change order more than an attractive but incomplete headline figure.
Approval documents come later, but plan for them now
A proposal may need a utility application, technical feasibility, connection agreement, meter specifications, test reports and inspection or charging approvals as applicable. The precise sequence depends on the chosen GERC arrangement, capacity, voltage and distribution licensee procedure. The 2026 regulation includes an activity chart and model agreements; it does not give every factory the same fixed meter list or exemption. GERC Notification 11/2026. Ask the EPC to name who prepares each document and which client signatures or shutdowns are needed.
For electrical safety, the current CEA safety regulations and applicable state requirements must be considered. The CEA register also lists a 2026 amendment whose commencement is stated as 1 April 2027. Do not treat that later effective date as already operative for a November or December 2026 connection. CEA safety regulations register. The engineer should confirm the rule set on the actual design and commissioning date.
Common document mistakes
One roof photograph in place of a survey. It cannot verify strength, hidden clips, purlins or water tightness. Use it for orientation, then commission the structural review.
A bill average in place of load matching. Monthly kWh hides shift schedules and low-load days. Interval data or a clearly stated proxy is needed to estimate direct use.
An SLD that has never been updated. It may omit parallel transformers, new boards or DG changes. Have qualified staff verify the installed network before the final tie-in is specified.
A tariff copied from another plant. Use this consumer’s licensee, category and current schedule. Contract demand, time-of-use and other charges can differ.
Unclear roof rights. An owner-approved installation, structural sign-off and roof warranty are three separate questions. Assign each to the appropriate party.
A proposal that hides exclusions. Ask whether strengthening, meter and CT/PT work, utility charges, roof repair, downtime and taxes are included or conditional. The answer should be written, not inferred.
A practical handoff to the EPC
Create one folder with bills, meter-data, SLD, roof, site-photos, production and permissions. Give each file a date and roof or meter identifier. Add a one-page note listing missing records and known changes since the latest drawing. This small amount of organisation prevents a bidder from modelling the wrong meter or an obsolete roof block. Keep sensitive operational information with the parties who need it and ask how the EPC will handle access to it.
The first response should identify a preliminary size range only if its assumptions are stated. The next step is a roof and electrical survey, followed by a revised technical and commercial proposal. If an answer depends on a utility approval or structural investigation, label it that way. This is how a factory gets a decision-ready proposal without pretending every unknown has been solved at the first meeting.
Get a load-based proposal for my plant. Send the starter pack through the business enquiry form on industrial solar, or call +91 63904 05060. Heaven Green Energy is a Surat solar company founded in 2017. The more clearly the plant identifies its actual meter, roof and operating pattern, the more useful the proposed next survey will be.