A factory shed may look like a large, empty solar site from the yard. The roof tells a different story: skylights, smoke vents, gutters, fragile sheets, old patch repairs, crowded electrical routes and areas the maintenance team must still reach. Those details change the usable area, safe construction method and price. A useful first quote begins with a disciplined roof record, even if the final design still needs an engineer’s survey.
This checklist is for a factory owner, facilities manager or plant engineer collecting information before requesting an industrial rooftop solar proposal. It is a pre-quote check, not permission to climb on a roof or certify its structure. Do not send untrained staff onto a shed. Use existing drawings, ground-level photographs and safe access records; commission a qualified structural and electrical review for the final design. The point is to give bidders the same site facts and expose unknowns early.
A one-page roof record for bidders
| Item | What to record | Who should confirm it |
|---|---|---|
| Roof identity | Shed number, address, grid connection, owner | Facilities/finance |
| Structure | Framing type, span, purlin spacing, drawings, changes | Structural engineer |
| Covering | Sheet/slab type, age, repairs, fragile areas | Facilities and specialist survey |
| Clear area | Approximate dimensions, obstructions, access routes | Surveyor/designer |
| Water | Drainage paths, leak history, gutters | Facilities team |
| Loads | Existing equipment and known suspended loads | Structural engineer |
| Electrical | Main board, transformer, cable routes, isolation | Electrical engineer |
| Use | Shift pattern, shutdown dates, future expansion | Plant management |
| Access | Ladders, platforms, cranes, permit-to-work | Safety officer |
| Rights | Ownership, lease, landlord permission | Owner/tenant counsel |
Mark every line as measured, documented, or needs verification. That label is more useful than a neat but unsupported number. A bidder can price a survey or identify a design dependency when uncertainty is visible.
1. Confirm which roof and which electricity connection
Many industrial sites have several sheds built in different years, sometimes with different owners or meter arrangements. Number the roofs on a site plan and identify the connection the proposed plant would serve. Include the consumer name and connection details in the confidential RFQ pack, not on a public webpage. If a landlord owns the shed and a tenant pays the bill, record both roles. Roof permission, equipment ownership and the utility applicant may be different entities.
The Gujarat Electricity Regulatory Commission’s 2026 DRES regulations provide the current framework for relevant new distributed renewable projects. A lawful-possession pathway in a regulation does not replace private roof consent. Before buying modules, establish who can allow fixings, maintenance access, electrical works and removal at the end of a lease. If a specific connection or site is outside the rooftop route, the designer should identify the applicable process instead of forcing the project into a familiar form.
2. Find the structural drawings—and record what changed
Original drawings can show column grid, purlins, trusses, roof pitch and design loads. They may no longer describe the actual shed after extensions, mezzanines, process equipment or previous repairs. Ask the facilities team for as-built drawings and inspection reports, then note alterations. If drawings do not exist, tell bidders plainly. A site survey and measured structural assessment must then be scoped before a final design or fixed construction price.
Do not assume that a roof can carry solar because it has carried people or rain for years. Solar adds dead load and changes wind effects through modules, rails and attachments. The anchoring method has to suit the actual structural members and covering. A qualified structural engineer should assess the design load path from module to main frame. The sales proposal’s panel count cannot substitute for that calculation.
3. Identify the roof covering and its condition
Record whether the roof is a concrete slab, metal sheet, fibre-cement sheet or a mix. Note approximate installation dates, known repairs, brittle areas and leaks. Take photographs from safe positions. The covering affects attachment options, water-tightness work, safe access and long-term maintenance. A design that assumes a new metal sheet may be unsuitable for an ageing or fragile covering.
Ask who will inspect and repair the roof before installation. A solar contractor can be asked to include penetrations and reinstatement, but an existing roof defect may be a separate project. Put that distinction in the quote. Otherwise a leak discovered after commissioning can become an argument over whether it predated the array.
4. Measure usable area, not total footprint
Begin with roof dimensions but subtract what the designer cannot use: skylights, smoke or heat vents, HVAC units, roof access, safety zones, drainage maintenance strips, parapet effects and any required fire paths. Shading from a taller adjoining shed or chimney can reduce suitable area even when there is physical room for panels. Record orientation and roof pitch, then ask bidders to show a layout with setbacks and access routes.
Do not convert square metres to kW using a single rule of thumb and treat it as a promise. Module size, spacing, tilt, wind design and obstructions change capacity. A preliminary number can guide a discussion; the drawing and structural check set the credible capacity. Ask the bidder to explain each area removed from the layout.
5. Check skylights, vents and emergency systems
Roof openings often serve workers below. Blocking a skylight can change daylight in a production area. Obstructing a smoke vent can impair a safety system. Mark every opening and its service clearance on the roof plan. Tell bidders what must remain operable, accessible and unshaded. Have the site’s safety and fire teams review the proposal before approval.
A walkway is not spare solar area. It may be needed to reach vents, inspect roof sheets or respond to an electrical fault. Maintain access to existing equipment and future maintenance points. Ask the designer to show how a person safely reaches each inverter, combiner box or module row without improvising a route across fragile sheets.
6. Follow the water
Map the roof slope, gutters, downpipes and known ponding areas. Photograph water stains or leak repair locations. Mounting feet and cable routes must not create new water paths or block drainage. Ask how penetrations are sealed, what materials are used and who inspects them after the first monsoon. Include a roof-restoration obligation in the installation scope.
Drainage is a maintenance issue as well as a construction issue. Panels can make gutters harder to clean. A good layout leaves practical access, and the O&M plan says who removes debris. If the roof is already at the end of its life, replacing it before installing solar may avoid removing the array for a separate roofing project soon afterward. That sequencing decision deserves a costed comparison rather than a sales slogan.
7. Look for shade over a full working day
Take photographs of the roof and surroundings at different times if safe and practical. Note chimneys, lift rooms, tanks, neighbouring buildings and planned structures. A noon photograph on one day does not capture seasonal sun angles or process equipment that operates intermittently. Ask bidders to model shade and identify assumptions. If a shadow affects only part of the array, the string and MPPT arrangement can matter.
Keep the shade assessment attached to the proposal. When two bids predict different generation from the same roof, ask whether they used the same obstacles, weather assumptions and array layout. Generation is a model output, not a guaranteed number simply because it appears in a quote.
8. Map the electrical route and the connection point
Locate the transformer, main board, meter room, cable trays and likely inverter positions. Ask an electrical engineer to describe spare capacity, existing protection, isolation constraints and the proposed point of interconnection. Long or difficult cable routes can change cost and losses. Penetrations through production zones may require special shutdowns or containment.
The quote should include a preliminary single-line diagram and the scope of protection, earthing, cables, distribution equipment and monitoring. An MNRE rooftop technical specification illustrates how much equipment a complete installation can include. Its terms were written for a specific programme; use it as a scope prompt, then let the qualified engineer specify this plant’s requirements. The CEA safety regulations index should be checked for rules in force on the work date. The 2026 safety amendment commences on 1 April 2027.
9. Compare generation with the factory’s load shape
Ask the electrical or finance team for at least recent monthly bills and, ideally, interval load data. Record weekdays, weekends, seasonal shutdowns and planned additional machinery. A solar plant produces during daylight; factory demand may not match it. The design needs an explicit self-consumption or export assumption. If export approval is uncertain, ask the bidder to model the permitted case and the curtailment case separately.
Do not infer savings from capacity alone. Tariff category, demand charges, energy charges, applicable duties, export settlement and actual production all matter. This pre-quote checklist is meant to reveal the data needed for a proper analysis. It is not a substitute for a tariff and bill review.
10. Plan safe construction without stopping the plant unexpectedly
Record access gates, yard traffic, loading bays, crane positions, material storage, emergency routes and allowed work hours. A rooftop project may require a lifting plan and temporary exclusion zone below. Ask the plant safety officer to identify permit-to-work requirements, fall protection rules, hot work rules and electrical isolation procedures. Bidders should price and schedule around these conditions.
Write down the shutdown windows the site can realistically offer. A contractor should not assume an uninterrupted installation if the plant operates around the clock. Conversely, the factory should not offer a weekend isolation that its production manager cannot approve. A credible project programme has named access dependencies.
11. Identify ownership, lease and future roof plans
If the shed is leased, assemble the lease, roof-use consent and any lender or owner restrictions for legal review. Who may install and own the array? Who insures the roof and equipment? May the contractor access the site during a tenant dispute? What happens when the lease ends before the equipment’s expected service life? These questions affect financing and the design of removable or transferable equipment.
Also ask whether the business plans to expand the shed, add rooftop HVAC, replace sheets or change the electrical connection. A solar layout that consumes every open area can frustrate a known expansion. Tell bidders which zones must remain available and which future changes are only possibilities. This is part of the design basis, not an afterthought.
12. Decide what evidence a final quote must contain
The RFQ should request a roof layout, major equipment schedule, preliminary structural approach, electrical single-line diagram, utility-approval responsibilities, energy model assumptions, itemised price, exclusions and milestone schedule. It should say when a detailed survey and signed structural calculation will be delivered. Ask bidders to show any provisional amounts for roof repair or reinforcement. If they cannot know those costs yet, a conditional offer is more honest than an invented fixed price.
Require a deviations list. The bidder should state where the proposal differs from the RFQ or relies on unverified facts. This is especially important for old sheds with incomplete drawings. A proposal can be commercially useful while still conditional; the problem is hiding the condition. Use the same record for each bidder so the comparison is fair.
Send this pack before asking for a price
Put the site plan, roof identifiers, photographs, available structural drawings, electrical single-line diagram, bills, shift pattern, lease/consent status and safety access rules in a controlled data pack. Remove personal data that bidders do not need. Mark unknowns visibly. Ask for a site visit where practical and state which details the contractor must independently verify. Then compare not only price but also how each bidder resolved the unknowns.
Use the shed roof solar checklist to record the roof facts before requesting a final quote.
The adjacent homeowner roof-inspection guide is about a different building type. A factory shed brings longer spans, operational shutdowns, industrial electrical interfaces and roof-rights questions that need their own review. Our industrial solar team can use this pre-quote pack to prepare a load-based proposal. Use the business form on this page to Get a load-based proposal for my plant, and include the roof and bill information you already have.