A factory solar contract can look complete on the day it is signed and still leave the hardest questions unanswered. Who pays if the roof needs reinforcement? What exactly counts as commissioning? What happens when the utility approval takes longer than expected? Which data will show whether the system is producing what the proposal described? These are contract questions, not details to solve at the last minute on site.
This guide is a reading checklist for a factory owner, plant head or finance team buying an engineering, procurement and construction (EPC) project. It is not a substitute for a lawyer’s review of the final document or an engineer’s review of the design. Its purpose is to make both reviews more useful. A sound contract should turn the proposed plant into a set of measurable deliverables, named responsibilities, dated decisions and workable remedies.
Start by identifying which agreement you are signing
An EPC contract is generally a contract to deliver a defined installation for an agreed price and scope. A power purchase agreement (PPA), in contrast, centres on who owns the plant and sells its electricity over time. A lease, an operation and maintenance (O&M) agreement, a utility application and equipment warranties may sit alongside either structure. A single proposal can casually refer to all of them as “the solar agreement.” Do not accept that shorthand in the signature pack.
Write the document map on the first page of your review: EPC agreement, scope and technical schedules, price schedule, milestone schedule, drawings, exclusions, warranties, O&M agreement, land or roof permission, and documents the distribution licensee requires. Then give each attachment a version and date. If a drawing changes after the price is agreed, you need to know which drawing controls. If a salesperson’s yield estimate conflicts with the technical schedule, you need an order of precedence. An unsigned presentation should not quietly become the only source of a performance promise.
For a leased shed, first confirm who has authority to permit the work and for how long. The Gujarat Electricity Regulatory Commission’s 2026 Distributed Renewable Energy Sources regulations address applicants with lawful possession in the relevant rooftop context. That does not, by itself, grant a tenant permission under a private lease to fix structures to a roof. Put owner consent, access rights, removal duties and the lease-end outcome in writing before treating a roof as available.
The contract map: twelve clauses to read together
| Clause or schedule | Question to ask before signing | Evidence to attach |
|---|---|---|
| Scope of work | Is the contractor supplying a complete working plant, or only the named equipment? | Itemised bill of quantities and exclusions |
| Design basis | Which load, roof, wind, electrical and export assumptions support the design? | Surveys, calculations and approved drawings |
| Equipment | What exact minimum specifications and substitution rules apply? | Datasheets, make/model approval process |
| Approvals | Who applies, pays, responds to queries and tracks each approval? | Approval matrix and application list |
| Price and changes | Which costs are fixed, provisional or subject to a written change order? | Price schedule and variation form |
| Programme | What starts the clock, and which events extend it? | Dated milestones and dependency list |
| Site access | When can work happen without stopping production? | Access and shutdown plan |
| Testing | Which tests establish mechanical completion, energisation and acceptance? | Test plan and signed records |
| Output | Is there a specific performance guarantee, and under what conditions? | Calculation method and data source |
| Payment | Which evidence releases each payment? | Milestone certificates |
| Defects and warranty | Who responds, replaces equipment and bears access costs? | Warranty and service schedule |
| Exit and disputes | What happens on suspension, termination or a prolonged disagreement? | Notice and dispute clauses |
This table is a review tool. It is not a suggestion that every contractor offers every remedy. Its value lies in asking each bidder the same question and seeing where an answer is missing.
1. Scope: define a functioning system, not a pile of boxes
“Supply and install rooftop solar” is too thin for a factory purchase. The technical schedule should name modules, inverters, mounting structure, DC and AC cabling, cable routing, protection devices, earthing, monitoring, labels, drawings, tests, training and handover documents. It should also say who supplies civil work, access equipment, crane time, shutdown coordination and any upgrade at the interconnection point. A buyer should be able to trace every necessary interface to an owner.
An MNRE rooftop solar technical specification is a useful illustration of how wide a complete system scope can be: it lists modules, inverters, structures, cables, distribution boxes, protection, earthing and associated works. That document was issued for a particular programme; it should inform a commercial checklist, not be copied into a factory contract as if the programme’s conditions automatically apply.
Check exclusions word by word. Roof strengthening is often the most important one. Ask whether the price includes structural assessment, reinforcement design and work, leak remediation, replacement of fragile sheets, safe access and restoration after penetrations. If these are excluded, budget and responsibility must be assigned elsewhere. “Client scope” is a cost and schedule item, not a note to ignore.
The scope should also cover as-built drawings and equipment serial-number lists. These are practical operating records: when a fault occurs or a module warranty is claimed years later, the plant team needs to know what was actually installed.
2. The design basis: make the assumptions visible
The proposed capacity alone does not describe a design. The contractor should record the roof areas used, obstructions and shading, usable electrical load profile, proposed interconnection, export assumptions, inverter placement, cable routes and any known space constraints. Ask for the drawings and calculations that make the capacity credible. Have a qualified structural engineer review loads and attachment details for the actual shed before fabrication.
If a proposal assumes export or banking, check the current utility and regulatory position for the specific connection. Gujarat’s 2026 distributed renewable energy regulations matter for new projects in their scope, and the application pathway and settlement assumptions can differ by arrangement. The phrase “net metering available” should never be the sole design basis for a factory investment. Record what approval is required and what the fallback is if the approved configuration differs.
Design changes need a process. A change can be legitimate when a roof survey finds weak purlins or an inverter model becomes unavailable. The contract should require a written description of technical effect, price effect, programme effect and approval before the change is made. An equivalent model is not necessarily equivalent in efficiency, protection functions, service network or warranty terms.
3. Equipment and substitutions: name the floor
The equipment schedule should specify performance and compliance requirements, then identify approved products or an approval route. For modules, record rated capacity, technology, applicable test and safety certifications, warranty documents, serial traceability and any domestic-content condition that actually applies. For inverters, record AC rating, voltage range, number of MPPTs, protection functions, monitoring interface, enclosure rating and service support. For structures, ask for corrosion protection, fastener specification, roof interface and structural calculations.
Do not write a specification that merely says “Tier 1 module” or “premium inverter.” Those are sales descriptions, not an acceptance test. Equally, avoid locking in a single brand without considering supply risk. A useful substitution clause says that the contractor must propose an alternative with a comparison sheet, supporting certificates and warranty documents, and obtain the buyer’s written consent. It should also state whether a substitution changes price or delivery.
The MNRE specification names module test families such as IEC 61215 / IS 14286 and IEC 61730 in its programme context. The applicable requirements for a particular factory project must be checked against current procurement, BIS and programme rules. The contract should identify those requirements rather than assume a certificate mentioned in an old proposal still suffices.
4. Approvals and the utility interface: assign the work
Make a simple approvals register. List each required permission or inspection, the applicant, documents needed, fees, submission date, response owner and whether it is a condition for starting work or energising. The contractor may prepare drawings and forms while the consumer signs or pays. The contract should say which party is doing which step. If a third party or distribution licensee controls timing, neither side should be deemed to have guaranteed that third party’s date.
The key is a controlled response to delay. Specify who follows up, when the other party must supply missing documents, how a material approval change affects design and how long either side waits before a formal variation or termination right arises. A clause that treats every utility delay as the contractor’s fault is often unrealistic. A clause that gives unlimited extension with no reporting is no better for the buyer. Ask for a dated status log.
Where electrical safety approvals apply, ensure the scope includes the documentation and tests the competent authority requires. The CEA safety regulations page lists the 2023 regulations and a 2026 amendment. The 2026 amendment states an 1 April 2027 commencement date; do not apply its new provisions to a December 2026 project as though already in force. Ask your engineer and counsel to identify the requirements in force on the actual installation and energisation dates.
5. Price, taxes and variations: know the real contract value
Put the base price, applicable taxes, utility fees, statutory charges, roof repairs, reinforcement, meter changes, monitoring subscription, O&M and consumables on one cost sheet. Mark every item included, excluded or provisional. If a cost cannot be known until survey or utility response, state how it will be quoted and approved. A low EPC price can become a high project cost if the exclusions are broad.
Milestone payments should match verifiable work. An advance may support procurement, but the buyer should understand what security or title rights protect it. A delivery milestone can require invoices and a serial-number inventory. Installation can require signed progress records. Final payment can follow testing and handover. The exact percentages are a commercial negotiation; no universal allocation is safe to copy from another project.
The variation clause is the pressure valve. Require a written instruction before extra work, a priced proposal, the effect on completion date and a signed acceptance. Define emergency safety work separately so that a genuine hazard can be made safe without turning every change into an after-the-fact invoice.
6. Programme and site access: plan around production
A factory is an operating site. The contract should identify access hours, isolation and shutdown windows, permit-to-work requirements, roof work rules, material storage and contact people on both sides. Who authorises a shutdown? Who coordinates with the electrical team? Can a crane enter the yard when trucks are loading? These details affect the real programme more than the number of weeks on a sales slide.
Distinguish milestones: survey, design freeze, procurement, roof preparation, mechanical completion, electrical completion, inspection, grid approval, energisation, performance test and handover. Assign dependencies. “Completion within 90 days” is ambiguous if the period starts before the roof is available or if grid approval has no date. A workable contract identifies the trigger and records legitimate extensions.
Liquidated damages, if included, need a defined trigger, cap, exclusions and method of calculation. A penalty for late physical installation should not be confused with a claim for missed generation when the plant is installed but cannot yet energise for reasons outside the contractor’s control. Have counsel test enforceability against the contract structure and applicable law.
7. Acceptance and performance: define the measurement
Commissioning is not a single switch-on moment. Separate mechanical completion, electrical test, permission to energise, initial operation, performance testing and final acceptance. The test plan should identify the test instruments, responsible witnesses, pass/fail criteria, reports, correction process and retest procedure. Require copies of protection settings, insulation and continuity results, inverter commissioning records, as-built single-line diagram and monitoring access.
If a performance ratio or generation guarantee is offered, ask how it is measured. Define the reference weather data, exclusions for grid outage or owner shutdown, measurement period, data quality, degradation assumptions and remedy. A guarantee written as “expected annual units” without a measurement method may be hard to administer. An SECI tender annexure on functional guarantees shows why formal projects define test methods and timing; its specific terms belong to that procurement, so use it as a reference for questions, not as an automatic standard for a factory roof.
Also ask who owns and can export the monitoring data. A buyer should be able to see inverter-level status, generation history and fault logs and retain access if the original service provider changes. If a portal subscription ends, clarify whether the system still operates and what data can be recovered.
8. Warranty, O&M and the exit
Separate the contractor’s workmanship warranty, equipment manufacturers’ warranties and any O&M service obligation. Their periods, claim processes and remedies differ. Who diagnoses a failure? Who pays to reach or remove an inverter? Who pays crane or roof access costs when a module warranty is accepted? A manufacturer may replace a component without covering labour. Record the interface so the plant owner does not spend months between two suppliers.
The O&M schedule should set inspection frequency, cleaning responsibilities, response and restoration process, spare-parts policy, monitoring review and annual reporting. Do not accept an undefined promise of “complete maintenance.” If response time is important, agree a specific service level and the conditions under which it applies. Avoid assuming that Heaven Green Energy or any contractor offers a specific time unless it appears in the signed offer.
Termination language matters even when everyone expects the project to finish. If the roof becomes unavailable, an approval is refused, a party defaults or the buyer sells the facility, what documents and paid-for equipment are handed over? Is there a cure period? Can another contractor complete the work? Who may use drawings and monitoring data? A clear exit protects both parties and can keep a project from becoming stranded.
A practical contract review before the signature meeting
Take the latest offer and mark three colours: defined, conditional, and missing. For each missing or conditional item, ask for either a revised schedule or a written explanation of who bears the risk. In the meeting, use the following prompts:
- Show the final roof plan, structural sign-off pathway and electrical single-line diagram.
- List every exclusion that could require the buyer to spend more money.
- Identify every approval, fee, applicant and expected decision point.
- Show the exact module, inverter and structure specifications and substitution rule.
- Walk through one payment claim and the evidence needed to release it.
- Explain the difference between installed, energised, tested and accepted.
- Demonstrate how performance will be measured and how data will be exported.
- Name the person who handles a defect after handover and the cost of access.
- Show what happens if the roof or utility approval changes the design.
- Confirm which documents win when the proposal and signed schedules conflict.
Enter the same bidder inputs in the EPC quote comparison tool to surface exclusions and assumption gaps.
This review may reveal that two quotes with the same capacity are pricing different projects. That is useful information before a purchase order, when you can still correct it. Our industrial solar team can build a load-based proposal around the actual plant, roof and electrical connection. Use the business enquiry form on this page to Get a load-based proposal for my plant. Bring your electricity bills, roof drawings if available and the existing offer; the first conversation can then focus on the contract decisions that matter.