Writing Module and Inverter Specs Into a Factory Solar RFQ

A factory solar request for quotation (RFQ) can ask three EPC firms for “a 500 kW rooftop system” and receive three prices that cannot be compared.

A factory solar request for quotation (RFQ) can ask three EPC firms for “a 500 kW rooftop system” and receive three prices that cannot be compared. One may price a different inverter arrangement, another may exclude the monitoring connection, and a third may allow a substitute module without telling you what that does to the layout. The capacity line is a useful start. It is not a technical specification.

This guide helps a plant engineering or procurement team write the module and inverter sections of an RFQ. It offers a structure and sample questions, not a universal equipment prescription. Your engineer should adapt values to the roof, electrical connection, load, environment and current rules. The aim is to make bidders disclose what they actually offer and make departures visible before purchase.

Write the design basis before choosing a model

First give bidders the same information. Attach recent electricity bills and, if possible, interval load data. Identify operating hours, shutdown days, existing sanctioned load, transformer and main distribution board details, approximate roof area, roof type, drawings, known shading and the location of the grid connection. Say whether export is envisaged, prohibited or still to be confirmed. If the applicant is a tenant, explain what roof access and landlord consent are available. A bidder cannot make a reliable inverter or module selection when the electrical and physical constraints are hidden.

Keep facts separate from assumptions. “The shed roof is believed to be 4,000 square metres” is different from a measured usable roof area after skylights, fire access, gutters and maintenance clearances. “No export assumed pending utility confirmation” is different from a permitted zero-export design. Ask bidders to state their own design assumptions in a single schedule and mark each one for buyer verification.

Gujarat’s 2026 Distributed Renewable Energy Sources regulations govern relevant arrangements and replaced older rules for new applications in scope. The RFQ should call for a design that fits the actual application route and current licensee requirements. It should not carry a copied 2016 net-metering assumption into a 2026 procurement.

The comparison sheet every bidder should return

FieldBidder’s responseWhy the buyer needs it
DC module capacity and module countkWp, quantity, rated WpReveals the proposed array size and roof footprint
AC inverter capacity and countkW/kVA, units, phaseShows the AC side and redundancy arrangement
DC/AC ratioNumber and design explanationMakes clipping and oversizing assumptions visible
Module make and exact modelManufacturer, model, datasheet revisionPrevents a generic brand-level offer
Inverter make and exact modelManufacturer, model, datasheet revisionLets engineers check grid and protection features
String and MPPT layoutDrawing or scheduleTests shade, mismatch and voltage design
Certificates and registrationDocument number, model covered, validityAvoids an unrelated certificate being attached
Warranty and local supportParties, durations, exclusions, claim routeIdentifies the real service path
Monitoring and data accessSignals, retention, export methodSupports acceptance and O&M
SubstitutionsAllowed only with written comparison and consentKeeps the bid basis intact

Ask for this table with every offer. A bidder may have a good reason for a different solution, but the difference needs to be explicit. Do not rank quotations by price until each has answered the same questions.

Module specification: describe performance and evidence

An RFQ should ask for a module’s rated power under standard test conditions, efficiency, technology, physical size, weight, electrical ratings, temperature coefficients and tolerance. Those data let the designer fit a real roof and electrical string, rather than count panels from a sales brochure. Include the applicable product and safety standards, their current BIS or IEC equivalents, and the exact certificate or registration evidence to be supplied at delivery. The MNRE rooftop technical specification names standards such as IEC 61215 / IS 14286 and IEC 61730 for its programme. That is a useful prompt for an engineer; the RFQ must still check the requirements applicable to this project and procurement date.

Do not equate a factory’s product catalogue with a certificate for the exact model proposed. Ask the bidder to identify the model designation on the certificate and match it to the bill of materials. Require a serial-number list at delivery so the installed fleet can be traced. Where a project specifically requires Domestic Content Requirement (DCR) modules, state that condition and its documentary basis separately. A generic “Made in India” phrase does not establish compliance with a specific scheme’s cell-and-module requirement.

The specification should address the site environment. Coastal salt, chemical fumes, dust or unusually high roof temperature can affect selection and warranty interpretation. Ask what environmental qualification or manufacturer approval supports the proposed module at this location. Do not invent a universal minimum temperature coefficient or corrosion class; ask the engineer to set a project-specific threshold. A lab qualification is evidence about a test, not a guarantee that every roof exposure has been modelled.

Write how modules will be delivered and accepted. Packaging, visible damage, flash-test or nameplate data, quantity, serial numbers, certificates and storage conditions can be checked before installation. If the EPC firm offers a substitute, require a side-by-side comparison of rated power, efficiency, dimensions, electrical values, warranty, applicable registration and price. This protects the layout: a different panel footprint may shift walkways, wind loading or string count even when its wattage looks identical.

A sample module clause to adapt

The bidder shall identify the exact module manufacturer and model proposed, attach the current datasheet and applicable product safety and performance certification for that model, and state the required domestic-content status, if any. The final delivered model and serial numbers shall be recorded in the as-built package. Any change in model shall require a written technical comparison and buyer approval before procurement. The EPC bidder shall state resulting effects on design, energy estimate, programme and price.

This is a drafting example, not legal language ready to sign. Have your technical and legal teams align it with the actual procurement.

Inverter specification: start with the grid and the load

For each inverter ask for exact model, rated AC output, voltage and frequency operating range, DC input limits, maximum current per input, MPPT count and range, efficiency curve, cooling method and enclosure rating. Ask for the grid-interface and protection functions required for the proposed connection, with evidence from the manufacturer’s documentation. An inverter must match the string design and the facility’s electrical system, not simply “accept solar power.”

The DC/AC ratio deserves an explanation, not a universal target pasted into an RFQ. Designers may place more DC module capacity than AC inverter nameplate capacity because modules rarely operate at nameplate output all day. The resulting clipping, inverter loading and energy yield depend on site weather, orientation, temperature and load/export arrangements. Ask each bidder to show monthly modelled generation, clipping assumptions and the sensitivity to a different AC size. If an industrial connection cannot export, ask how curtailment is modelled and controlled.

Inverter placement matters. Record proposed equipment-room or outdoor locations, ventilation, access clearance, cable length, flood or water exposure, fire-safety coordination and communication path. A convenient drawing location may be inaccessible to service technicians or too far from the array. Ask for the arrangement in a plan and single-line diagram. A plant engineering team should review those drawings against its own operations and safety rules.

Monitoring is part of the inverter specification. Ask what data are available at inverter and site level, whether the buyer can export historical records, how long data are retained, whether an internet outage affects generation, and who pays for connectivity or a portal subscription. If the owner cannot retrieve production and alarm history, an annual performance discussion becomes an argument over screenshots. Define data access at commissioning and after the O&M agreement ends.

A sample inverter clause to adapt

The bidder shall identify each inverter manufacturer and model and provide the datasheet, grid-interface documentation, protection settings proposal and a string-to-MPPT schedule. The design submission shall show DC/AC ratio, clipping assumptions, AC connection, communication architecture and monitoring access. Before energisation, the EPC contractor shall supply approved settings, commissioning test records and buyer administrator access to operational data.

Again, the actual protection settings and approvals belong to the qualified engineer and relevant authority. Do not turn a sample clause into an electrical design instruction.

Ask for the drawings that make the specifications testable

An equipment schedule without a design is hard to evaluate. The RFQ response should include at least a preliminary roof layout, module orientation and row spacing, setback and access depiction, string diagram, single-line diagram, major cable routes and proposed inverter locations. Ask for calculations or design notes supporting structural load, voltage limits, protection and cable sizing. The final package should identify who signs and approves each calculation.

For the roof, the design basis must address the actual sheet, purlin or slab system. A module that is technically excellent can still be inappropriate if its mounting arrangement loads a weak roof or interferes with drainage. Ask bidders to flag structural dependencies before giving a fixed construction date. The roof survey and qualified structural review should be explicit steps, with a change process if the original assumptions fail.

For the electrical interface, ask the bidder to show the point of interconnection, protective devices and isolation arrangement. The CEA regulations index provides the 2023 safety regulations and 2026 amendment. The 2026 amendment commences on 1 April 2027, so the engineer must assess the rules in force at the relevant stage instead of assuming every 2026 provision already applies. The RFQ can require compliance with applicable current law without guessing the final inspection date.

Standards and lists: specify what applies, not everything you found online

The strongest RFQ is not the one with the longest standards appendix. It is the one where each cited standard or registration has a reason and a verification method. A residential-subsidy specification, an export-project tender and an industrial self-consumption roof do not necessarily share every condition. Ask the designer to create a compliance matrix with the rule, why it applies, the component affected, the evidence required and the person checking it.

For modules, relevant questions may include product certification, safety, current ALMM applicability and whether a scheme’s DCR condition attaches. For inverters, relevant questions include product and grid-code requirements and any utility-prescribed settings. Verify current official lists and notices at the time of procurement because model approvals and scheme conditions can change. A bidder should not be allowed to swap an approved model with an unverified one under a vague “equivalent” clause.

Warranties and support: compare the remedy, not just the years

Ask for the product warranty document and the performance warranty document for modules, and the manufacturer warranty for inverters. Record the start date, exclusions, claim proof, transfer conditions and whether replacement labour and access are covered. A long duration printed on a slide says little about the cost of removing a failed module from a high shed roof. Ask who diagnoses faults, who submits the claim and who owns the temporary loss of generation.

The EPC workmanship warranty is separate. It concerns installation work, roof interfaces and electrical assembly, within its actual terms. The O&M arrangement is separate again. Ask for a responsibility matrix for the first year and afterward. If remote monitoring flags an alarm on a Sunday, the agreement should tell the plant team whom to contact and what the promised response means; do not assume a service level that has not been offered in writing.

Bid evaluation: normalise before you score

After bids arrive, make a three-column technical evaluation: compliant, deviation, and clarification needed. First resolve missing certificates, roof assumptions, protection details and exclusions. Then compare DC and AC capacity, credible generation model, warranty route, monitoring access and total scope. Only after that should price be assessed. A cheaper offer that excludes roof strengthening or monitoring is a different offer.

Ask each bidder to price alternatives separately, such as a different module model or a second inverter arrangement, while keeping a common base case. This lets procurement see the cost of the choice rather than accidentally comparing an alternative with the base design. Record every clarification in the bid file and carry accepted changes into the final contract schedules. The RFQ is useful only if the signed equipment schedule still matches the winning offer.

The factory solar RFQ template gives bidders a common set of roof, electrical and commercial questions.

Our industrial solar team can review your load, roof and proposed electrical connection to prepare a plant-specific proposal. Use the business enquiry form on this page to Get a load-based proposal for my plant. Bring the latest bills, available roof drawings and any competing specifications; the conversation can begin with the design choices the RFQ has exposed.

Written by
Heaven Green Energy

Founded in Surat in 2017. Head office at Utran, Surat. Heaven Green files PM Surya Ghar and DISCOM paperwork for its customers.

About Heaven Green Energy
Ready to Go Solar?

Plan solar around your factory

Share recent electricity bills, the load profile and roof details so the proposal can address your site.

Call WhatsApp